4243 N SHADYGLADE AVE 91604

Certificate Information: 4243 N SHADYGLADE AVE 91604

Application / Permit
24010-10000-05038
Plan Check / Job No.
B24LA35200
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - NEW TWOS TORY SFD WITH ATTACHED OPEN TRELLIS
Permit Issued
Issued on 5/9/2025
Issuing Office
Current Status
Issued on 5/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 KHUONG TRUONG
Corrections Issued 12/31/2024 KHUONG TRUONG
Quality Review Completed 1/10/2025 PRANITA SHAH
Plan Check Approved 5/9/2025 STARR CHEN
Issued 5/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/13/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/13/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/17/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/31/2025 CARLOS AGUILERA
ZI Cleared 2/21/2025 JASON CHAN
Hydrant and Access approval Cleared 4/17/2025 RUEL COLE

Contact Information

Architect Phakos,, Cynthia; Lic. No.: NA23352       ,
Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B       ,
Contractor Ground Up Builders; Lic. No.: 911849-B       ,
Engineer Yates,, Gerald; Lic. No.: C73972 6309 DEL AMO BLVD      LAKEWOOD, CA 90713

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/5/2025 Approved JUAN VALENZUELA
Underground Mechanical 7/30/2025 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/15/2025 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/21/2025 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/25/2025 Conditional Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 8/27/2025 Conditional Approval JUAN VALENZUELA
Special/Order Compliance 9/26/2025 Approved CHRISTOPHER MORFIN
Underground Mechanical 9/26/2025 Partial Approval JUAN VALENZUELA
Deputy Steel/Welding 10/14/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/26/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 12/24/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 1/14/2026 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/2/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 2/2/2026 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/3/2026 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 2/3/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/3/2026 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 2/3/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 2/3/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 2/11/2026 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/17/2026 Corrections Issued NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 2/17/2026 Approved NICHOLAS TROWBRIDGE
Wood Frame 2/17/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Insulation 2/20/2026 Not Ready for Inspection MICHAEL CORTEZ
BUILDING-Rough-Frame 2/25/2026 Approved CHRISTOPHE COCHRAN
Wood Frame 2/25/2026 Approved CHRISTOPHE COCHRAN
Insulation 3/2/2026 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 3/10/2026 Approved CHRISTOPHE COCHRAN
Insulation 3/10/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 3/10/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/31/2026 Approved CHRISTOPHE COCHRAN
Pre-Inspection 4/14/2026 Approved CHRISTOPHE COCHRAN
Pre-Inspection 5/8/2026 Approved CHRISTOPHE COCHRAN