11921-11923 W HAMLIN ST 91606

Certificate Information: 11921-11923 W HAMLIN ST 91606

Application / Permit
24010-10000-05032
Plan Check / Job No.
B24VN24110
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY 2-UNIT ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). 13D FIRE SPRINKER THROUGH-OUT.
Permit Issued
Issued on 4/8/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 DANIEL YIP
Corrections Issued 12/7/2024 DANIEL YIP
Quality Review Completed 12/9/2024 GARO TELMI
Applicant returned to address corrections 1/16/2025 DANIEL YIP
Applicant returned to address corrections 3/11/2025 DANIEL YIP
Plan Check Approved 3/26/2025 DANIEL YIP
No Progress 3/26/2025 DANIEL YIP
Plan Check Approved 3/26/2025 DANIEL YIP
Issued 4/8/2025 APPLICANT
CofO in Progress 2/19/2026 JOSE AVILA
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/7/2025 RYAN CASTRO
Sewer availability Cleared 1/7/2025 RYAN CASTRO
Construction within easement Cleared 1/29/2025 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 3/13/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/5/2025 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/9/2025 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 6/10/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 6/12/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 7/25/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 7/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 7/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 7/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 7/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Rough-Elec/Plmb/HVAC 7/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 7/25/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Approved JOSE AVILA
Interior/Exterior Lathing 8/4/2025 Not Ready for Inspection JOSE AVILA
Shower Pan 8/4/2025 Approved JOSE AVILA
Interior/Exterior Lathing 8/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/21/2025 Corrections Issued JOSE AVILA
HVAC-Rough 8/21/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/21/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 9/3/2025 Approved JOSE AVILA
HVAC-Rough 9/3/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 9/9/2025 Partial Approval JOSE AVILA
Green Building Rough 9/9/2025 Approved JOSE AVILA
PLUMBING-Rough 9/9/2025 Approved JOSE AVILA
Verify Sprinkler Sign Off 9/9/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 10/20/2025 Approved JOSE AVILA
Footing/Foundation/Slab 10/20/2025 Approved JOSE AVILA
Insulation 10/20/2025 Approved JOSE AVILA
Drywall Nailing 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Final 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/29/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/4/2025 Approved JOSE AVILA
ELECTRICAL-Final 11/4/2025 Approved JOSE AVILA
Green Building Final 11/4/2025 Approved JOSE AVILA
HVAC-Final 11/4/2025 Approved JOSE AVILA
PLUMBING-Final 11/4/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready JOSE AVILA
Service/Power Release 11/4/2025 Approved JOSE AVILA
Smoke Detectors 11/4/2025 Approved JOSE AVILA
Final 2/17/2026 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Required JOSE AVILA