2561 W LAS FLORES DR 90041
Certificate Information: 2561 W LAS FLORES DR 90041
- Application / Permit
- 24010-10000-05018
- Plan Check / Job No.
- B24LA34968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 4/1/2026
- Issuing Office
- Metro
- Current Status
- Issued on 4/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | STARR CHEN |
| Corrections Issued | 12/17/2024 | STARR CHEN |
| Quality Review Completed | 12/17/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/12/2025 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 12/22/2025 | STARR CHEN |
| Applicant returned to address corrections | 1/5/2026 | STARR CHEN |
| Plan Check Approved | 1/28/2026 | STARR CHEN |
| Issued | 4/1/2026 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 3/14/2025 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 3/28/2025 | RUEL COLE |
| Address approval | Cleared | 4/2/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/3/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/1/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 10/1/2025 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 10/2/2025 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 10/2/2025 | MIGUEL ORNELAS |
| Permit | Cleared | 10/3/2025 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 1/28/2026 | STARR CHEN |
Contact Information
| Contractor | Simcity Construction, Inc.; Lic. No.: 1027407-B | 3350 W OLYMOIC BLVD #202 LOS ANGELES, CA 90019 |
| Engineer | Kwei,, Peter; Lic. No.: C72100 | 1306 N HAWTHORN WY AZUSA, CA 91702 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/24/2026 | Approved | RONNIE MEDINA |
| Underground Mechanical | 4/24/2026 | Partial Inspection | RONNIE MEDINA |
| Excavation/Setback/Form/Re-Bar | 4/30/2026 | Corrections Issued | RONNIE MEDINA |
| Footing/Foundation/Slab | 4/30/2026 | Corrections Issued | RONNIE MEDINA |
| Excavation/Setback/Form/Re-Bar | 5/4/2026 | Approved | RONNIE MEDINA |
| Footing/Foundation/Slab | 5/4/2026 | Approved | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Partial Approval | RONNIE MEDINA |
| Deputy Wood Construction | 6/23/2026 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2026 | Partial Approval | RONNIE MEDINA |
| ELECTRICAL-Rough | 6/30/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 6/30/2026 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/1/2026 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/17/2026 | Not Ready for Inspection | GEM DE OCAMPO |