7824 S BRIGHTON AVE 90047
Certificate Information: 7824 S BRIGHTON AVE 90047
- Application / Permit
- 24010-10000-04961
- Plan Check / Job No.
- B24LA34279
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] (N) 2-STORY STRUCTURE WITH ADU ON GROUND FLOOR AND RECREATION ROOM AT 2ND FLOOR. DETACHED ADU PER GC 66323(a)(2).
- Permit Issued
- Issued on 11/14/2025
- Issuing Office
- Current Status
- Issued on 11/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | ADRIANA LOPEZ |
| Corrections Issued | 2/28/2025 | ADRIANA LOPEZ |
| Quality Review Completed | 3/4/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 6/11/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 7/23/2025 | ADRIANA LOPEZ |
| Issued | 11/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 3/24/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 3/25/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 5/1/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/1/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Neeraj Mittal; Lic. No.: 1127454-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 11/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/11/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 1/6/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 1/6/2026 | Corrections Issued | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 1/12/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 1/12/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Conditional Approval | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/20/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/23/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/3/2026 | Partial Approval | JOHN QUINTANILLA |
| HVAC-Rough | 4/3/2026 | Partial Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/3/2026 | Approved | JOHN QUINTANILLA |
| Shower Pan | 4/3/2026 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/8/2026 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 4/8/2026 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/8/2026 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 4/8/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/10/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 4/10/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 4/15/2026 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 4/28/2026 | Approved | ALEX COLIN |