524 W 121ST ST 90044
Certificate Information: 524 W 121ST ST 90044
- Application / Permit
- 24010-10000-04958
- Plan Check / Job No.
- B24LA31524
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- EPLAN. NEW 2-CAR GARAGE
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | PRANITA SHAH |
| Corrections Issued | 11/20/2024 | PRANITA SHAH |
| Quality Review Completed | 12/3/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/9/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 4/22/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 5/21/2025 | PRANITA SHAH |
| Plan Check Approved | 7/31/2025 | PRANITA SHAH |
| Issued | 10/15/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Gabor Design Group Inc The; Lic. No.: 842370-B | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2025 | Approved | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 12/16/2025 | Conditional Approval | BEN MOLSTAD |
| Deputy Methane Barrier | 12/19/2025 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/22/2025 | Partial Approval | DAVID FEILER |
| Deputy Methane Barrier | 1/21/2026 | Conditional Approval | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 3/16/2026 | Conditional Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 3/20/2026 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 4/8/2026 | Conditional Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Partial Approval | EUGENE CASSIDY |
| Special/Order Compliance | 4/9/2026 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/28/2026 | Approved | BEN MOLSTAD |
| METHANE-Rough | 4/28/2026 | Approved | BEN MOLSTAD |