5933-5933 1/2 W COMEY AVE 90034

Certificate Information: 5933-5933 1/2 W COMEY AVE 90034

Application / Permit
24010-10000-04950
Plan Check / Job No.
B24LA34121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan:1) Building A: new three story duplex with roof deck and attached Rec. Room and Garage at 1st Floor Construction shall not commence without CALOSHA permit. Supplemental permit required to capture the CALOSHA clearance once it is obtained.
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 ARSALAN SHABESTARI
Corrections Issued 12/11/2024 ARSALAN SHABESTARI
Quality Review Completed 12/18/2024 PRANITA SHAH
Plan Check Approved 4/25/2025 ARSALAN SHABESTARI
Issued 5/8/2025 APPLICANT
CofO in Progress 6/1/2026 RYAN SALAZAR
Permit Finaled 6/4/2026 RICHARD STEINBACH
CofO Issued 6/4/2026 RICHARD STEINBACH
Permit Finaled 6/4/2026 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/30/2024 KURT CORRAL
SB8 RUD Cleared 1/6/2025 OLIVIA JIN
Low Impact Development (LID) Cleared 1/7/2025 ERNEST TSE
Address approval Cleared 1/10/2025 ADRIAN SANCHEZ
ZI Cleared 1/14/2025 JAZMIN ROQUE
Eng Process Fee Ord 176,300 Cleared 1/17/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/17/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/17/2025 ADRIAN SANCHEZ

Contact Information

Contractor West Peak Renovations; Lic. No.: 1106420-B       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/18/2025 Corrections Issued BOBBY KEY
Underground Mechanical 6/18/2025 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 6/20/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 6/20/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/15/2025 Approved EVAN COOPER
Sewer 8/8/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval STEPHANIE SWANSON
Drywall Nailing 8/22/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Partial Approval EVAN COOPER
Drywall Nailing 9/3/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved DANIEL VERA
ELECTRICAL-Rough 11/19/2025 Not Ready for Inspection EVAN COOPER
HVAC-Rough 11/19/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 11/19/2025 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 11/21/2025 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 11/21/2025 Not Ready for Inspection EVAN COOPER
Green Building Rough 11/21/2025 Not Ready for Inspection EVAN COOPER
HVAC-Rough 11/21/2025 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 11/21/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 11/21/2025 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 11/21/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 11/25/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 11/25/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/25/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 11/25/2025 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 12/3/2025 Approved EVAN COOPER
ELECTRICAL-Rough 12/3/2025 Approved EVAN COOPER
Green Building Rough 12/3/2025 Approved EVAN COOPER
HVAC-Rough 12/3/2025 Approved EVAN COOPER
MERV13>=Rough 12/3/2025 Approved EVAN COOPER
PLUMBING-Rough 12/3/2025 Approved EVAN COOPER
Insulation 12/12/2025 Approved EVAN COOPER
Shower Pan 12/12/2025 Approved EVAN COOPER
Interior/Exterior Lathing 12/23/2025 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 12/30/2025 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 12/30/2025 Not Ready for Inspection ANDREW NAVE
Drywall Nailing 1/6/2026 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 1/6/2026 Partial Approval WILBER ROSALES
Special/Order Compliance 1/6/2026 Partial Inspection DAKOTA LOW
Drywall Nailing 2/17/2026 Approved WILBER ROSALES
Underground Mechanical 3/27/2026 Partial Approval WILBER ROSALES
ELECTRICAL-Final 5/4/2026 Not Ready for Inspection WILBER ROSALES
HVAC-Final 5/4/2026 Not Ready for Inspection WILBER ROSALES
Service/Power Release 5/4/2026 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Final 5/6/2026 Approved WILBER ROSALES
HVAC-Final 5/6/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Final 5/6/2026 Not Ready for Inspection WILBER ROSALES
Service/Power Release 5/6/2026 Approved WILBER ROSALES
Final 5/7/2026 Not Ready for Inspection WILBER ROSALES
Green Building Final 5/7/2026 Approved WILBER ROSALES
HVAC-Final 5/7/2026 Approved WILBER ROSALES
MERV13>=Final 5/7/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Final 5/7/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Not Required WILBER ROSALES
Final 5/28/2026 OK to Issue CofO RYAN SALAZAR
MERV13>=Final 5/28/2026 Approved RYAN SALAZAR
Smoke Detectors 5/28/2026 Approved RYAN SALAZAR