13612 W HESBY ST 91423
Certificate Information: 13612 W HESBY ST 91423
- Application / Permit
- 24010-10000-04933
- Plan Check / Job No.
- B24LA33952
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(B) AND LAMC 12.22 A.33 (c), (d), AND (g) ***13D SPRINKLER REQUIRED PER PLAN***
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- Issued on 7/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | KHUONG TRUONG |
| Corrections Issued | 12/18/2024 | KHUONG TRUONG |
| Quality Review Completed | 12/19/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 5/13/2025 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/18/2025 | KHUONG TRUONG |
| Plan Check Approved | 7/22/2025 | KHUONG TRUONG |
| Issued | 7/28/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 12/19/2024 | NATHAN ROMINE |
| Address approval | Cleared | 12/24/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/24/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/8/2025 | RYAN CASTRO |
Contact Information
| Architect | Lopez,, Craig Joseph; Lic. No.: NA14263 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/31/2025 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/14/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| Special/Order Compliance | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 9/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 9/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 11/14/2025 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 12/8/2025 | Partial Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/23/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/15/2026 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/15/2026 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/15/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/9/2026 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 2/9/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 2/9/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/9/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 2/9/2026 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 2/9/2026 | Approved | JAVIER RAMOS JR |
| Shower Pan | 2/24/2026 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/26/2026 | Approved | JAVIER RAMOS JR |