6627 S DENVER AVE 90044

Certificate Information: 6627 S DENVER AVE 90044

Application / Permit
24010-10000-04919
Plan Check / Job No.
B24LA33748
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE PORTION OF (E) DETACHED GARAGE AND CONVERT REMAINING PORTION WITH IRREGULAR SHAPED ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH ATTACHED PATIO COVER.
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
CofO Issued on 10/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/13/2024 ALEC MOUSAKHANIAN
Corrections Issued 12/13/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 3/14/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 3/18/2025 ISIS ARGUETA
Applicant returned to address corrections 3/19/2025 KAMYAR EMAMI
Applicant returned to address corrections 4/2/2025 KAMYAR EMAMI
Plan Check Approved 4/2/2025 KAMYAR EMAMI
Issued 5/19/2025 APPLICANT
CofO in Progress 10/17/2025 RAUL BARAJAS
No Progress 10/19/2025 DEROLD HAUFF
CofO in Progress 10/19/2025 DEROLD HAUFF
Permit Finaled 10/25/2025 DEROLD HAUFF
Permit Finaled 10/25/2025 DEROLD HAUFF
CofO Issued 10/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/13/2024 ALEC MOUSAKHANIAN
Construction near power lines Cleared 2/24/2025 RIDWAN HARDY
Construction within easement Cleared 2/24/2025 RIDWAN HARDY
Address approval Cleared 2/28/2025 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 2/28/2025 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 3/11/2025 TREVOR QUAN
Sewer availability Cleared 3/11/2025 TREVOR QUAN

Contact Information

Contractor Van Buren Maintenance; Lic. No.: 1106794-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 6/16/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 6/16/2025 Not Ready for Inspection BARRY HACHE
Footing/Foundation/Slab 7/8/2025 Approved BARRY HACHE
PLUMBING-Rough 7/8/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 7/9/2025 Approved BARRY HACHE
PLUMBING-Rough 7/9/2025 Approved BARRY HACHE
ELECTRICAL-Rough 8/4/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Corrections Issued BARRY HACHE
MERV13>=Rough 8/4/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 8/8/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Approved BARRY HACHE
PLUMBING-Rough 8/8/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 8/12/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 8/12/2025 Not Ready for Inspection BARRY HACHE
MERV13>=Rough 8/12/2025 Approved BARRY HACHE
PLUMBING-Rough 8/12/2025 Approved BARRY HACHE
Underground Mechanical 8/12/2025 Approved BARRY HACHE
Interior/Exterior Lathing 8/14/2025 Approved RONNIE MEDINA
BUILDING-Rough-Frame 8/19/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 8/19/2025 Approved BARRY HACHE
HVAC-Rough 8/19/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 8/25/2025 Approved BARRY HACHE
HVAC-Rough 8/25/2025 Approved BARRY HACHE
Insulation 8/27/2025 Corrections Issued RONNIE MEDINA
Insulation 8/28/2025 Approved ANTHONY RAMOS
Drywall Nailing 9/3/2025 Approved RONNIE MEDINA
Sewer 9/3/2025 Not Ready for Inspection RONNIE MEDINA
Underground Mechanical 9/3/2025 Partial Approval RONNIE MEDINA
Interior/Exterior Lathing 9/5/2025 Approved BARRY HACHE
Sewer 9/5/2025 Approved BARRY HACHE
ELECTRICAL-Final 10/2/2025 Corrections Issued BARRY HACHE
HVAC-Final 10/2/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 10/8/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 10/8/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 10/8/2025 Approved BARRY HACHE
MERV13>=Final 10/8/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 10/8/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 10/8/2025 Approved BARRY HACHE
ELECTRICAL-Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 10/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/15/2025 Approved RAUL BARAJAS
Final 10/15/2025 OK to Issue CofO RAUL BARAJAS
Green Building Final 10/15/2025 Approved RAUL BARAJAS
HVAC-Final 10/15/2025 Approved RAUL BARAJAS
MERV13>=Final 10/15/2025 Approved RAUL BARAJAS
PLUMBING-Final 10/15/2025 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved RAUL BARAJAS