- eplan: (N) 33'-9" X 32' DETACHED ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEER NFPA 13D REQUIRED THROUGHOUT (REQUESTED BY FIRE DEPT)
- Permit Issued
- Issued on 6/29/2025
- Issuing Office
- Current Status
- CofO Issued on 5/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 12/12/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 5/13/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/30/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/2/2025 | ALEC MOUSAKHANIAN |
| Issued | 6/29/2025 | APPLICANT |
| CofO in Progress | 5/19/2026 | EUGENE CASSIDY |
| CofO in Progress | 5/19/2026 | EUGENE CASSIDY |
| CofO in Progress | 5/20/2026 | EUGENE CASSIDY |
| Permit Finaled | 5/20/2026 | ANSON MAGLASANG |
| CofO Issued | 5/20/2026 | ANSON MAGLASANG |
| Permit Finaled | 5/20/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2025 | VISHAL MANDALIA |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | VISHAL MANDALIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | VISHAL MANDALIA |
| Sewer availability | Cleared | 3/3/2025 | VISHAL MANDALIA |
| Hydrant and Access approval | Cleared | 3/18/2025 | JERRY KAO |
Contact Information
| Contractor | Next Level Home Improvements; Lic. No.: 1120800-B | , |
| Engineer | Banning,, George Kwame; Lic. No.: NA53074 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Partial Approval | EUGENE CASSIDY |
| METHANE-Barrier | 7/30/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/30/2025 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/31/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | EUGENE CASSIDY |
| Insulation | 8/12/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Partial Approval | EUGENE CASSIDY |
| Sewer | 8/21/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 8/25/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/17/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/17/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/17/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/17/2025 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 9/17/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/17/2025 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/17/2025 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 9/17/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/26/2025 | Approved | EUGENE CASSIDY |
| Insulation | 9/26/2025 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 9/26/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/3/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/3/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/9/2025 | Approved | EUGENE CASSIDY |
| Service/Power Release | 11/3/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 2/13/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/13/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 2/13/2026 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 2/13/2026 | Approved | EUGENE CASSIDY |
| Final | 3/6/2026 | Corrections Issued | EUGENE CASSIDY |
| Final | 5/14/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 5/19/2026 | OK to Issue CofO | EUGENE CASSIDY |