- NEW DETACHED 26' 1" X 26' 8" ACCESSORY DWELLING UNIT WITH ATTACHED 3' 5" X 9' 5" PATIO COVER PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 8/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 12/5/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/4/2025 | MADISON ODELL |
| Plan Check Approved | 3/17/2025 | MADISON O'DELL |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 8/4/2025 | BARRY HACHE |
| Permit Finaled | 8/11/2025 | DEROLD HAUFF |
| CofO Issued | 8/11/2025 | DEROLD HAUFF |
| Permit Finaled | 8/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/2/2025 | RIDWAN HARDY |
| Address approval | Cleared | 1/17/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/24/2025 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Banning,, George Kwame; Lic. No.: NA53074 | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/15/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 4/17/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 4/17/2025 | Approved | BARRY HACHE |
| Wood Frame | 4/28/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 5/1/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 5/12/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 5/14/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 5/19/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 5/19/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 5/19/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 5/21/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 5/21/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 5/21/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 5/23/2025 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 5/23/2025 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 5/23/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 5/28/2025 | Approved | BARRY HACHE |
| Wood Frame | 5/28/2025 | Approved | BARRY HACHE |
| Green Building Rough | 5/29/2025 | Approved | BARRY HACHE |
| Insulation | 5/29/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 6/2/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 6/4/2025 | Approved | ANTHONY RAMOS |
| Service/Power Release | 7/2/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 7/14/2025 | Corrections Issued | BARRY HACHE |
| Final | 7/14/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 7/14/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 7/14/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 7/14/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Required | BARRY HACHE |
| Service/Power Release | 7/14/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 7/14/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 7/21/2025 | Conditional Approval | LUIS CASTRO |
| Final | 7/21/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 7/21/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 7/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 7/21/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 7/21/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 7/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 7/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Service/Power Release | 7/24/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 7/28/2025 | Not Ready for Inspection | BARRY HACHE |
| Service/Power Release | 7/28/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 7/30/2025 | Corrections Issued | BARRY HACHE |
| Service/Power Release | 7/30/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 8/1/2025 | OK to Issue CofO | BARRY HACHE |
| Service/Power Release | 8/1/2025 | Approved | BARRY HACHE |