2504 S MIDVALE AVE 90064
Certificate Information: 2504 S MIDVALE AVE 90064
- Application / Permit
- 24010-10000-04873
- Plan Check / Job No.
- B24LA33322
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Proposed detached ADU PER STATE LAW 1 OF 2
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Current Status
- Issued on 5/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | KHUONG TRUONG |
| Corrections Issued | 12/13/2024 | KHUONG TRUONG |
| Quality Review Completed | 12/17/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/21/2025 | KHUONG TRUONG |
| Plan Check Approved | 2/27/2025 | KHUONG TRUONG |
| No Progress | 5/13/2025 | KHUONG TRUONG |
| Plan Check Approved | 5/14/2025 | KHUONG TRUONG |
| Issued | 5/19/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2024 | DARIN LAM |
| Specific Plan | Cleared | 12/27/2024 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 1/3/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2025 | DARIN LAM |
| Sewer availability | Cleared | 1/6/2025 | DARIN LAM |
| Specific Plan | Cleared | 1/7/2025 | RICHARD WOO |
| Specific Plan | Cleared | 1/7/2025 | RICHARD WOO |
| Construction near power lines | Cleared | 2/13/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/13/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 4/25/2025 | VASIL MIHALEV |
Contact Information
| Contractor | F N Construction Inc; Lic. No.: 905630-B | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/30/2025 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 7/2/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/7/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 8/7/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 8/14/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/14/2025 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 8/14/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/21/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/21/2025 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 8/21/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 9/12/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Drywall Nailing | 9/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Drywall Nailing | 9/19/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/19/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 11/5/2025 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 11/5/2025 | Approved | KIRK SANDERS |
| Gas Test | 2/17/2026 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/1/2026 | Approved | RYAN SALAZAR |
| Final | 5/1/2026 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/1/2026 | Approved | RYAN SALAZAR |
| Green Building Final | 5/1/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 5/1/2026 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/1/2026 | SGSOV Not Ready | RYAN SALAZAR |
| Service/Power Release | 5/1/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 5/1/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 5/1/2026 | Approved | RYAN SALAZAR |