2504 S MIDVALE AVE 90064

Certificate Information: 2504 S MIDVALE AVE 90064

Application / Permit
24010-10000-04873
Plan Check / Job No.
B24LA33322
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Proposed detached ADU PER STATE LAW 1 OF 2
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
Issued on 5/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/12/2024 KHUONG TRUONG
Corrections Issued 12/13/2024 KHUONG TRUONG
Quality Review Completed 12/17/2024 GARO TELMI
Applicant returned to address corrections 2/21/2025 KHUONG TRUONG
Plan Check Approved 2/27/2025 KHUONG TRUONG
No Progress 5/13/2025 KHUONG TRUONG
Plan Check Approved 5/14/2025 KHUONG TRUONG
Issued 5/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/26/2024 DARIN LAM
Specific Plan Cleared 12/27/2024 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 1/3/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/6/2025 DARIN LAM
Sewer availability Cleared 1/6/2025 DARIN LAM
Specific Plan Cleared 1/7/2025 RICHARD WOO
Specific Plan Cleared 1/7/2025 RICHARD WOO
Construction near power lines Cleared 2/13/2025 RIDWAN HARDY
Construction within easement Cleared 2/13/2025 RIDWAN HARDY
Grading Pre-Inspection Cleared 4/25/2025 VASIL MIHALEV

Contact Information

Contractor F N Construction Inc; Lic. No.: 905630-B       ,
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2025 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 6/23/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/30/2025 Partial Approval BOBBY KEY
Footing/Foundation/Slab 6/30/2025 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 7/2/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/7/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 8/7/2025 Corrections Issued DANIEL VERA
ELECTRICAL-Rough 8/14/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/14/2025 Approved ARAM AVEDISIAN
Special/Order Compliance 8/14/2025 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 8/21/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 8/21/2025 Partial Approval ARAM AVEDISIAN
HVAC-Rough 8/21/2025 Partial Approval ARAM AVEDISIAN
Insulation 9/12/2025 Corrections Issued JAYLIN GRAVITTE
Drywall Nailing 9/17/2025 Not Ready for Inspection DANIEL VERA
Drywall Nailing 9/19/2025 Approved EVAN COOPER
Interior/Exterior Lathing 9/19/2025 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 11/5/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 11/5/2025 Approved KIRK SANDERS
Gas Test 2/17/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/1/2026 Approved RYAN SALAZAR
Final 5/1/2026 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 5/1/2026 Approved RYAN SALAZAR
Green Building Final 5/1/2026 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 5/1/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Not Ready RYAN SALAZAR
Service/Power Release 5/1/2026 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 5/1/2026 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 5/1/2026 Approved RYAN SALAZAR