3875 E AGUILAR ST 90065

Certificate Information: 3875 E AGUILAR ST 90065

Application / Permit
24010-10000-04872
Plan Check / Job No.
B24LA33320
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 1-story detached ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 2/26/2025
Issuing Office
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 REZA HAGHIGHAT
Corrections Issued 12/1/2024 REZA HAGHIGHAT
Plan Check Approved 2/20/2025 REZA HAGHIGHAT
Issued 2/26/2025 APPLICANT
CofO in Progress 8/11/2025 DAVID WILLIAMS
Permit Finaled 8/12/2025 DEROLD HAUFF
CofO Issued 8/12/2025 DEROLD HAUFF
Permit Finaled 8/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2024 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 12/9/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/9/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/9/2025 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 1/16/2025 ALEXANDER HELFER
Miscellaneous Cleared 1/27/2025 ANNA VIDAL
Miscellaneous Cleared 1/27/2025 ANNA VIDAL
Supp. Use District POD/CDO/TDO Cleared 1/30/2025 ANDREA MAGANA-WITHERS
Disturb/Remove Protected Trees Cleared 2/3/2025 RICHARD SANCHEZ
Miscellaneous Cleared 2/3/2025 ALBERT TAM
GPI Written Notices Cleared 2/20/2025 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: NA64529       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2025 Approved DAVID WILLIAMS
Underground Mechanical 4/11/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Approved DAVID WILLIAMS
Insulation 4/14/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 4/29/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 4/29/2025 Approved DAVID WILLIAMS
HVAC-Rough 4/29/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 4/29/2025 Partial Approval DAVID WILLIAMS
Verify Sprinkler Sign Off 4/29/2025 Approved DAVID WILLIAMS
Insulation 5/12/2025 Corrections Issued REGINA MENDEZ
Interior/Exterior Lathing 5/12/2025 Approved REGINA MENDEZ
Drywall Nailing 5/15/2025 Approved REGINA MENDEZ
Insulation 5/15/2025 Approved REGINA MENDEZ
Deputy Wood Construction 5/20/2025 Conditional Approval REGINA MENDEZ
ELECTRICAL-Final 7/25/2025 Approved DAVID WILLIAMS
Final 7/25/2025 Corrections Issued DAVID WILLIAMS
HVAC-Final 7/25/2025 Approved DAVID WILLIAMS
PLUMBING-Final 7/25/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved DAVID WILLIAMS
Service/Power Release 7/25/2025 Approved DAVID WILLIAMS
Smoke Detectors 7/25/2025 Approved DAVID WILLIAMS
Final 7/31/2025 Not Ready for Inspection DAVID WILLIAMS
HVAC-Final 7/31/2025 Approved DAVID WILLIAMS
Final 8/11/2025 OK to Issue CofO DAVID WILLIAMS