3875 E AGUILAR ST 90065
Certificate Information: 3875 E AGUILAR ST 90065
- Application / Permit
- 24010-10000-04872
- Plan Check / Job No.
- B24LA33320
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New 1-story detached ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | REZA HAGHIGHAT |
| Corrections Issued | 12/1/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 2/20/2025 | REZA HAGHIGHAT |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 8/11/2025 | DAVID WILLIAMS |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 1/9/2025 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 1/16/2025 | ALEXANDER HELFER |
| Miscellaneous | Cleared | 1/27/2025 | ANNA VIDAL |
| Miscellaneous | Cleared | 1/27/2025 | ANNA VIDAL |
| Supp. Use District POD/CDO/TDO | Cleared | 1/30/2025 | ANDREA MAGANA-WITHERS |
| Disturb/Remove Protected Trees | Cleared | 2/3/2025 | RICHARD SANCHEZ |
| Miscellaneous | Cleared | 2/3/2025 | ALBERT TAM |
| GPI Written Notices | Cleared | 2/20/2025 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2025 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 4/11/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Approved | DAVID WILLIAMS |
| Insulation | 4/14/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/29/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 4/29/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 4/29/2025 | Approved | DAVID WILLIAMS |
| Insulation | 5/12/2025 | Corrections Issued | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/12/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 5/15/2025 | Approved | REGINA MENDEZ |
| Insulation | 5/15/2025 | Approved | REGINA MENDEZ |
| Deputy Wood Construction | 5/20/2025 | Conditional Approval | REGINA MENDEZ |
| ELECTRICAL-Final | 7/25/2025 | Approved | DAVID WILLIAMS |
| Final | 7/25/2025 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Final | 7/25/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 7/25/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 7/25/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 7/25/2025 | Approved | DAVID WILLIAMS |
| Final | 7/31/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| HVAC-Final | 7/31/2025 | Approved | DAVID WILLIAMS |
| Final | 8/11/2025 | OK to Issue CofO | DAVID WILLIAMS |