8337 N QUARTZ AVE 91306
Certificate Information: 8337 N QUARTZ AVE 91306
- Application / Permit
- 24010-10000-04869
- Plan Check / Job No.
- B24LA33298
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20' X 25' 2 STORY DETACHED SFD PER SB9 *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT ***
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- Issued on 3/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | CRYSTEL MAALOUF |
| Assigned to Zoning Architect | 12/5/2024 | KAREN MEZA-MORALES |
| Corrections Issued | 12/20/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/23/2024 | KEN GILL |
| Green Plans Picked Up | 12/24/2024 | APPLICANT |
| Building Plans Picked Up | 1/2/2025 | APPLICANT |
| Applicant returned to address corrections | 2/13/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/14/2025 | CRYSTEL MAALOUF |
| Issued | 3/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/26/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 1/16/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/16/2025 | GEVORK KARAPETYAN |
| Senate Bill 9 | Cleared | 3/4/2025 | ASHLEY RODARTE |
| Zoning Plan Check | Cleared | 3/6/2025 | KAREN MEZA-MORALES |
Contact Information
| Contractor | C B D Construction; Lic. No.: 552681-B | 26500 AGOURA ROAD BOX 848 CALABASAS, CA 91302 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2025 | Partial Approval | SCOTT SOBEL |
| Footing/Foundation/Slab | 4/18/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 6/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 6/25/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/25/2025 | Partial Approval | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 6/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/1/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 8/1/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 8/1/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 8/1/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 8/5/2025 | Approved | SCOTT SOBEL |
| Final | 8/5/2025 | Corrections Issued | SCOTT SOBEL |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Not Ready | JEFFREY HARTLINE |
| Final | 4/15/2026 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 4/15/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Not Required | JEFFREY HARTLINE |
| Service/Power Release | 4/15/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 4/15/2026 | Not Ready for Inspection | JEFFREY HARTLINE |