4416 N STANSBURY AVE 91423

Certificate Information: 4416 N STANSBURY AVE 91423

Application / Permit
24010-10000-04775
Plan Check / Job No.
B24LA32154
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED 2 STORY ADU per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/31/2025
Issuing Office
Current Status
Issued on 3/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/16/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 JESSE VIDUYA
Corrections Issued 12/6/2024 JESSE VIDUYA
Quality Review Completed 12/11/2024 CHAD DOI
Applicant returned to address corrections 3/4/2025 JESSE VIDUYA
Plan Check Approved 3/24/2025 JESSE VIDUYA
Issued 3/31/2025 APPLICANT

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 12/16/2024 GEORGIA SMITH
Address approval Cleared 12/17/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 2/12/2025 GEVORK KARAPETYAN
Roof/Waste drainage to street Cleared 2/13/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/20/2025 BIAINA HARITUNIAN

Contact Information

Contractor Marco Giovanni Brambilla; Lic. No.: 544844-B       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/30/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/3/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/7/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 11/13/2025 Approved MISAEL ESPARZA
Deputy Wood Construction 1/28/2026 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 1/29/2026 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 1/29/2026 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 2/2/2026 Corrections Issued MISAEL ESPARZA
Wood Frame 2/11/2026 Corrections Issued MISAEL ESPARZA
Wood Frame 2/12/2026 Partial Inspection MISAEL ESPARZA
Wood Frame 2/13/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/26/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 5/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/29/2026 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 5/29/2026 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 6/1/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 6/1/2026 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/1/2026 Approved MISAEL ESPARZA
ELECTRICAL-Rough 6/11/2026 Approved MISAEL ESPARZA
HVAC-Rough 6/11/2026 Approved MISAEL ESPARZA
PLUMBING-Rough 6/11/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/22/2026 Partial Approval MISAEL ESPARZA
Insulation 6/22/2026 Corrections Issued MISAEL ESPARZA
Shower Pan 6/22/2026 Approved MISAEL ESPARZA
Insulation 6/24/2026 Approved MISAEL ESPARZA
Shower Pan 6/24/2026 Approved MISAEL ESPARZA
Shower Pan 7/1/2026 Corrections Issued CHRISTOPHE COCHRAN
Drywall Nailing 7/7/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/7/2026 Approved MISAEL ESPARZA