2057 W NORWALK AVE 90041
Certificate Information: 2057 W NORWALK AVE 90041
- Application / Permit
- 24010-10000-04771
- Plan Check / Job No.
- B24LA32147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached garage with addition to an ADU.
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2024 | DANIEL SANJUAN |
| Corrections Issued | 12/17/2024 | DANIEL SANJUAN |
| Plan Check Approved | 2/17/2025 | DANIEL SANJUAN |
| Issued | 3/11/2025 | APPLICANT |
| CofO in Progress | 12/8/2025 | RONNIE MEDINA |
| Permit Finaled | 12/9/2025 | DEROLD HAUFF |
| Permit Finaled | 12/9/2025 | DEROLD HAUFF |
| CofO Issued | 12/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 1/7/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/7/2025 | JUSTIN BICOL |
| Construction near power lines | Cleared | 2/13/2025 | ENRIQUE ACOSTA |
| GPI Written Notices | Cleared | 2/17/2025 | DANIEL SANJUAN |
| Grading Pre-Inspection | Cleared | 2/17/2025 | DANIEL SANJUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 6/3/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/26/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 8/26/2025 | Corrections Issued | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Corrections Issued | DAVID WILLIAMS |
| Gas Test | 8/26/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| HVAC-Rough | 8/26/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 8/26/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 8/26/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 8/28/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 8/28/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 8/28/2025 | Approved | DAVID WILLIAMS |
| Insulation | 9/3/2025 | Corrections Issued | REGINA MENDEZ |
| Interior/Exterior Lathing | 9/3/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 9/10/2025 | Corrections Issued | ANTHONY RAMOS |
| Green Building Rough | 9/10/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 9/12/2025 | Partial Inspection | DAVID WILLIAMS |
| Drywall Nailing | 9/16/2025 | Approved | REGINA MENDEZ |
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Partial Inspection | RONNIE MEDINA |
| Shower Pan | 10/15/2025 | Approved | RONNIE MEDINA |
| Underground Mechanical | 10/15/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 10/17/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | RONNIE MEDINA |
| Final | 12/2/2025 | Corrections Issued | RONNIE MEDINA |
| Footing/Foundation/Slab | 12/2/2025 | Approved | RONNIE MEDINA |
| Green Building Final | 12/2/2025 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2025 | SGSOV Approved | RONNIE MEDINA |
| Service/Power Release | 12/2/2025 | Approved | RONNIE MEDINA |
| Smoke Detectors | 12/2/2025 | Approved | RONNIE MEDINA |
| Final | 12/5/2025 | OK to Issue CofO | RONNIE MEDINA |
| Service/Power Release | 12/5/2025 | Partial Inspection | RONNIE MEDINA |