14002 W OTSEGO ST 91423
Certificate Information: 14002 W OTSEGO ST 91423
- Application / Permit
- 24010-10000-04746
- Plan Check / Job No.
- B24LA31806
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER LAMC 12.22 A.33 (c) AND (d). ALL WORK PER EOR. ALL ELECTRIC BUILDING Fire Sprinkler System: (NFPA-13D) Thru-out
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Current Status
- Issued on 4/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2024 | DANIEL SANJUAN |
| Corrections Issued | 11/19/2024 | DANIEL SANJUAN |
| Plan Check Approved | 4/3/2025 | DANIEL SANJUAN |
| Issued | 4/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/6/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 12/9/2024 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/10/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: NA87698 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/8/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/15/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/15/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 6/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 6/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 6/10/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/12/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 6/18/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 7/1/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/11/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/11/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 7/11/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/21/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/21/2025 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 8/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/7/2026 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 1/7/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/7/2026 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 1/7/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/15/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/15/2026 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 1/15/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 1/15/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 1/15/2026 | Not Required | MISAEL ESPARZA |
| Smoke Detectors | 1/15/2026 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/20/2026 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Final | 1/20/2026 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 1/20/2026 | No Access for Inspection | MISAEL ESPARZA |
| Service/Power Release | 1/20/2026 | No Access for Inspection | MISAEL ESPARZA |
| Final | 2/4/2026 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 2/4/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 2/4/2026 | Not Required | MISAEL ESPARZA |