7850 N BABCOCK AVE 91605
Certificate Information: 7850 N BABCOCK AVE 91605
- Application / Permit
- 24010-10000-04724
- Plan Check / Job No.
- B24LA31664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 2/28/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | KHUONG TRUONG |
| Corrections Issued | 12/3/2024 | KHUONG TRUONG |
| Quality Review Completed | 12/10/2024 | KEN GILL |
| Building Plans Picked Up | 12/11/2024 | APPLICANT |
| Applicant returned to address corrections | 2/26/2025 | KHUONG TRUONG |
| Plan Check Approved | 2/28/2025 | KHUONG TRUONG |
| Issued | 2/28/2025 | APPLICANT |
| CofO in Progress | 10/6/2025 | VINCENT HANLEY |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 12/17/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2024 | KEVIN CHUNG |
| Construction near power lines | Cleared | 2/19/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 2/19/2025 | GEVORK KARAPETYAN |
| Sewer availability | Cleared | 2/26/2025 | KEVIN CHUNG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/20/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 3/20/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/27/2025 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 3/27/2025 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/1/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Deputy Drilled-In Anchors | 5/6/2025 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 5/6/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/6/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 5/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| MERV13>=Rough | 5/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 5/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/6/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/6/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 5/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/15/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/19/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/19/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 6/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 6/5/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 6/5/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/6/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 8/14/2025 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/3/2025 | Approved | VINCENT HANLEY |
| Final | 10/3/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 10/3/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 10/3/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 10/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 10/3/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 10/3/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 10/3/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/3/2025 | Not Ready for Inspection | VINCENT HANLEY |