6727 1/2 S 7TH AVE 90043

Certificate Information: 6727 1/2 S 7TH AVE 90043

Application / Permit
24010-10000-04704
Plan Check / Job No.
B24LA31463
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-Story Detached ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/23/2024
Issuing Office
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 ALEC MOUSAKHANIAN
Corrections Issued 11/18/2024 ALEC MOUSAKHANIAN
Plan Check Approved 12/13/2024 ALEC MOUSAKHANIAN
Issued 12/23/2024 APPLICANT
CofO in Progress 11/5/2025 SALVADOR MARTINEZ
Permit Finaled 11/10/2025 DEROLD HAUFF
CofO Issued 11/10/2025 DEROLD HAUFF
Permit Finaled 11/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/20/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 11/20/2024 JUSTIN BICOL
Construction near power lines Cleared 12/4/2024 TINA MIRANDA
Sewer availability Cleared 12/12/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/13/2024 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2025 Approved ALEJANDRO DE ARTOLA
Sewer 1/25/2025 Off-Hour Fees Due
PLUMBING-Rough 1/27/2025 Corrections Issued ANTHONY RAMOS
PLUMBING-Rough 1/28/2025 Partial Approval NICHOLAS LOPEZ
Sewer 1/28/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 1/29/2025 Partial Approval NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 2/10/2025 Partial Inspection LUIS CASTRO
Footing/Foundation/Slab 2/10/2025 Not Ready for Inspection LUIS CASTRO
Footing/Foundation/Slab 2/11/2025 Approved MICHAEL LEWIS
Wood Frame 3/5/2025 Not Ready for Inspection BARRY HACHE
Rough-Elec/Plmb/HVAC 3/19/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Approved MICHAEL LEWIS
HVAC-Rough 3/20/2025 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 3/20/2025 Not Ready for Inspection MICHAEL LEWIS
Sewer 3/20/2025 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 4/9/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 4/9/2025 Not Ready for Inspection WAYNE REGESTER
Rough-Elec/Plmb/HVAC 4/9/2025 Not Ready for Inspection WAYNE REGESTER
Verify Sprinkler Sign Off 4/9/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 4/14/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 4/17/2025 Partial Approval WAYNE REGESTER
PLUMBING-Rough 4/17/2025 Approved WAYNE REGESTER
HVAC-Rough 4/24/2025 Approved WAYNE REGESTER
Wood Frame 4/24/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 5/1/2025 Approved WAYNE REGESTER
Insulation 5/1/2025 Partial Approval WAYNE REGESTER
Sewer 5/1/2025 Approved WAYNE REGESTER
Drywall Nailing 5/6/2025 Corrections Issued ANTHONY RAMOS
Shower Pan 5/6/2025 Not Ready for Inspection ANTHONY RAMOS
Drywall Nailing 5/13/2025 Not Ready for Inspection ANTHONY RAMOS
Interior/Exterior Lathing 5/13/2025 Approved ANTHONY RAMOS
Shower Pan 5/13/2025 Approved ANTHONY RAMOS
Drywall Nailing 5/15/2025 Approved ANTHONY RAMOS
Service/Power Release 5/22/2025 Approved WAYNE REGESTER
Underground Mechanical 5/22/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 7/28/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 7/28/2025 Approved WAYNE REGESTER
HVAC-Final 7/28/2025 Approved WAYNE REGESTER
PLUMBING-Final 7/28/2025 Approved WAYNE REGESTER
Smoke Detectors 7/28/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 8/15/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 8/15/2025 Approved WAYNE REGESTER
Final 8/15/2025 Corrections Issued WAYNE REGESTER
Green Building Rough 8/15/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Required WAYNE REGESTER
Final 11/4/2025 OK to Issue CofO SALVADOR MARTINEZ