1458 W 17TH ST 90732

Certificate Information: 1458 W 17TH ST 90732

Application / Permit
24010-10000-04697
Plan Check / Job No.
B24LA31415
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. NEW 37'-4"X20'-2" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d) WITH 7'-7"X4'-0" STORAGE
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2024 APPLICANT
Assigned to Plan Check Engineer 11/19/2024 KAMYAR EMAMI
Corrections Issued 11/20/2024 KAMYAR EMAMI
Applicant returned to address corrections 12/11/2024 KAMYAR EMAMI
Plan Check Approved 1/2/2025 ARAMIK SHAHMIRZAIAN
Issued 1/6/2025 APPLICANT
CofO in Progress 6/17/2025 JOSEPH MCGARRY
Permit Finaled 6/17/2025 ANSON MAGLASANG
CofO Issued 6/17/2025 ANSON MAGLASANG
Permit Finaled 6/17/2025 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/10/2024 VASIL MIHALEV
Address approval Cleared 12/11/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 12/12/2024 JILVER MAZARIEGOS
Sewer availability Cleared 12/12/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 12/16/2024 JILVER MAZARIEGOS

Contact Information

Contractor Adu Building Company; Lic. No.: 1098802-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/30/2025 Partial Approval BEN MOLSTAD
Sewer 1/30/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 2/3/2025 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 2/3/2025 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 3/18/2025 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved JOSEPH MCGARRY
HVAC-Rough 3/18/2025 Approved JOSEPH MCGARRY
PLUMBING-Rough 3/18/2025 Approved JOSEPH MCGARRY
Wood Frame 3/18/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/26/2025 Approved JOSEPH MCGARRY
Green Building Rough 3/26/2025 Approved JOSEPH MCGARRY
Insulation 3/26/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/26/2025 Partial Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 3/26/2025 Approved JOSEPH MCGARRY
Drywall Nailing 4/1/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 5/6/2025 Approved JOSEPH MCGARRY
Sewer 5/19/2025 Approved BOBBY KEY
Underground Mechanical 5/23/2025 Approved JOSEPH MCGARRY
Final 6/13/2025 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 6/13/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 6/13/2025 Approved JOSEPH MCGARRY
Smoke Detectors 6/13/2025 Approved JOSEPH MCGARRY
Final 6/16/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Required JOSEPH MCGARRY