4521 N MARY ELLEN AVE 91423

Certificate Information: 4521 N MARY ELLEN AVE 91423

Application / Permit
24010-10000-04689
Plan Check / Job No.
B24LA29910
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan: (N) RECREATION ROOM
Permit Issued
Issued on 12/31/2024
Issuing Office
Current Status
Issued on 12/31/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/31/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 DANIEL YIP
Corrections Issued 11/9/2024 DANIEL YIP
Quality Review Completed 11/12/2024 GARO TELMI
Plan Check Approved 12/26/2024 DANIEL YIP
Issued 12/31/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/25/2024 CARLOS AGUILERA
Construction within easement Cleared 12/2/2024 WALTER RAMIREZ
ZI Cleared 12/12/2024 JACQUELINE TORRES

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/27/2026   

Inspection Request History

Underground Mechanical 3/24/2025 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 3/27/2025 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 3/27/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/1/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/1/2025 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/25/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 7/25/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 7/25/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 8/7/2025 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/7/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/7/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/7/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/29/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/29/2025 Partial Approval CHRISTOPHE COCHRAN
Insulation 9/5/2025 Approved JAVIER RAMOS JR
Drywall Nailing 9/23/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/23/2025 Partial Inspection CHRISTOPHE COCHRAN
Shower Pan 10/23/2025 Approved CHRISTOPHE COCHRAN
Final 7/1/2026 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 7/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/1/2026 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 7/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 7/1/2026 Approved CHRISTOPHE COCHRAN
Final 7/21/2026 Conditional Approval CHRISTOPHE COCHRAN
Green Building Final 7/21/2026 Approved CHRISTOPHE COCHRAN
Service/Power Release 7/21/2026 Approved CHRISTOPHE COCHRAN