1558-1560 E 109TH ST 90059

Certificate Information: 1558-1560 E 109TH ST 90059

Application / Permit
24010-10000-04682
Plan Check / Job No.
B24LA31334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePLAN. NEW 2-STORY DUPLEX WITH AN ATTACHED GARAGE.
Permit Issued
Issued on 4/28/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 KEVIN MORALES
Corrections Issued 11/18/2024 KEVIN MORALES
Quality Review Completed 11/19/2024 EUGENE BARBEAU
Plan Check Approved 4/9/2025 KEVIN MORALES
Issued 4/28/2025 APPLICANT
CofO in Progress 10/28/2025 ANTHONY EGSON
Permit Finaled 11/18/2025 ANSON MAGLASANG
CofO Issued 11/18/2025 ANSON MAGLASANG
Permit Finaled 11/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

Trees in Parkway Cleared 12/13/2024 MIGUEL ORNELAS
Hydrant and Access approval Cleared 12/17/2024 KURT CORRAL
Highway dedication Cleared 12/18/2024 DAVID LOPEZ
Low Impact Development (LID) Cleared 12/20/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 12/30/2024 DAVID LOPEZ
Address approval Cleared 1/2/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/2/2025 DAVID LOPEZ
Sewer availability Cleared 2/4/2025 AMBER CAMPBELL

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/28/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/28/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/30/2025 Approved ANTHONY EGSON
Sewer 5/30/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 6/16/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Not Ready for Inspection ANTHONY EGSON
Insulation 6/17/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 8/20/2025 Corrections Issued ANTHONY EGSON
HVAC-Rough 8/20/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/21/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/21/2025 Corrections Issued ANTHONY EGSON
Verify Sprinkler Sign Off 8/21/2025 Approved ANTHONY EGSON
Green Building Rough 8/25/2025 Approved ANTHONY EGSON
PLUMBING-Rough 8/25/2025 Corrections Issued ANTHONY EGSON
Sewer 8/25/2025 Corrections Issued ANTHONY EGSON
Insulation 8/27/2025 Corrections Issued ANTHONY EGSON
Sewer 8/27/2025 Approved ANTHONY EGSON
Insulation 8/29/2025 Approved ANSON MAGLASANG
Drywall Nailing 9/5/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/5/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 10/23/2025 Partial Approval ANTHONY EGSON
HVAC-Final 10/23/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/24/2025 Approved ANTHONY EGSON
Final 10/24/2025 OK to Issue CofO ANTHONY EGSON
PLUMBING-Final 10/24/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Required ANTHONY EGSON
Service/Power Release 10/24/2025 Approved ANTHONY EGSON
Smoke Detectors 10/24/2025 Approved ANTHONY EGSON