1723 S CORINTH AVE 1-42 90025

Certificate Information: 1723 S CORINTH AVE 1-42 90025

Application / Permit
24010-10000-04657
Plan Check / Job No.
B24LA31071
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan - NEW 5 STORY 42 UNITS (5 VLI + 36 LI) 100% AFFORDABLE HOUSING APARMTEENT PER 12.22 A25 INCENTIVES CalOSHA permit must be obtained before construction is commenced
Permit Issued
Issued on 5/6/2026
Issuing Office
Current Status
Issued on 5/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/7/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 MANUEL MONTUFAR
Assigned to Zoning Architect 11/14/2024 HAYDON CHAN
Corrections Issued 12/5/2024 MANUEL MONTUFAR
Quality Review Completed 12/5/2024 EUGENE BARBEAU
Plan Check Approved 1/9/2026 STARR CHEN
Issued 5/6/2026 APPLICANT

Permit Application Clearance Information

Hold Cleared 11/25/2024 MARIA VENDIVIL
Address approval Cleared 6/17/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/17/2025 CARLOS AGUILERA
Specific Plan Cleared 7/29/2025 RICHARD WOO
Green Code Cleared 8/4/2025 MANUEL MONTUFAR
DAS Clearance Cleared 8/21/2025 MANUEL MONTUFAR
Density Bonus Cleared 9/18/2025 ALYSSA FLORES
SB8 RUD Cleared 9/18/2025 ALYSSA FLORES
Fire Marshal Fire Life Safety Cleared 9/23/2025 MENOA AGHAJANI
Trees in Parkway Cleared 9/23/2025 RICHARD SANCHEZ
Hydrant and Access approval Cleared 10/8/2025 LAVEON RIDER
Sewer availability Cleared 11/3/2025 DIANA RENTERIA
CPC Cleared 11/21/2025 YINGSHI HUANG
Frnt yard landscape/Water mgmt Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Miscellaneous Cleared 11/21/2025 YINGSHI HUANG
Opn space landscape/Water mgmt Cleared 11/21/2025 YINGSHI HUANG
Permit Cleared 11/21/2025 CARLOS AGUILERA
"Q" conditions Cleared 11/24/2025 YINGSHI HUANG
Miscellaneous Cleared 11/24/2025 YINGSHI HUANG
Low Impact Development (LID) Cleared 12/2/2025 ERNEST TSE
Zoning Plan Check Cleared 12/8/2025 HAYDON CHAN
Roof/Waste drainage to street Cleared 12/15/2025 DAVID LOPEZ

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: NA30005       ,
Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Bregaudit,, Cesar Sibal; Lic. No.: L8382 22163 WIND FLOWER PL      SANTA CLARITA, CA 91390
Engineer Pirbadian,, Amir; Lic. No.: C72413 17514 VENTURA BLVD.   SUITE 206    ENCINO, CA 91346
Geologist Minas,, Shant; Lic. No.: GEO8859 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2026 Not Ready for Inspection DANIEL VARNUM
METHANE-Barrier 6/15/2026 Not Ready for Inspection DANIEL VARNUM
METHANE-Subgrade 6/15/2026 Not Ready for Inspection DANIEL VARNUM
METHANE-Barrier 7/7/2026 Approved DANIEL VARNUM
METHANE-Subgrade 7/7/2026 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 7/13/2026 Approved DANIEL VARNUM