5514 N FULTON AVE 91401
Certificate Information: 5514 N FULTON AVE 91401
- Application / Permit
- 24010-10000-04655
- Plan Check / Job No.
- B24LA31036
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: New construction of a 1-story detached ADU 800 S.F. per state law. NFPA 13D fire sprinklers thru out.
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- Current Status
- Issued on 12/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | DANIEL SMILEY |
| Corrections Issued | 11/14/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 12/13/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/18/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 12/26/2024 | LUKE GONZALES |
| Issued | 12/27/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/5/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/8/2024 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/4/2025 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 2/4/2025 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/18/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Rough | 4/18/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 4/18/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/18/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 4/18/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 4/18/2025 | Approved | RYAN SALAZAR |
| Insulation | 5/28/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 6/3/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/16/2025 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 6/23/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 7/15/2025 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/31/2025 | Approved | KEVIN BERBERYAN |