12520 W KLING ST 91604
Certificate Information: 12520 W KLING ST 91604
- Application / Permit
- 24010-10000-04642
- Plan Check / Job No.
- B24LA29256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] NEW 1-STORY ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) - BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 12/30/2024
- Issuing Office
- Current Status
- Issued on 12/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/7/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/20/2024 | TU HUA |
| Plan Check Approved | 12/30/2024 | MAHNAZ NOURHASHEMI |
| Issued | 12/30/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/22/2024 | RYAN CASTRO |
| Low Impact Development (LID) | Cleared | 12/12/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/12/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 12/18/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 12/18/2024 | WALTER RAMIREZ |
| ZI | Cleared | 12/19/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 6/9/2025 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/20/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/24/2025 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/26/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/21/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/22/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/26/2025 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/15/2025 | Approved Pending GreenApproval | JUAN VALENZUELA |
| Green Building Rough | 10/15/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 10/15/2025 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/15/2025 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/24/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Pre-Inspection | 10/27/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 10/30/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 10/30/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/13/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/3/2026 | Approved | CHRISTOPHE COCHRAN |