17101 W MCCORMICK ST 91316

Certificate Information: 17101 W MCCORMICK ST 91316

Application / Permit
24010-10000-04617
Plan Check / Job No.
B24LA30692
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel and addition to SFD. NFPA 13D sprinkler throughout
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
Issued on 5/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 ARSALAN SHABESTARI
Corrections Issued 11/12/2024 ARSALAN SHABESTARI
Quality Review Completed 11/22/2024 YOUNG KIM
Applicant returned to address corrections 2/9/2025 ARSALAN SHABESTARI
Plan Check Approved 5/7/2025 ARSALAN SHABESTARI
Issued 5/7/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/27/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/3/2024 RYAN CASTRO
Sewer availability Cleared 12/3/2024 RYAN CASTRO
Hydrant and Access approval Cleared 12/5/2024 PATRICK PEREZ
Trees in Parkway Cleared 12/23/2024 MIGUEL ORNELAS
Low Impact Development (LID) Cleared 2/26/2025 ERNEST TSE
Permit Cleared 2/26/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 3/14/2025 RYAN CASTRO

Contact Information

Contractor E B R Construction Inc; Lic. No.: 941088-B       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/9/2025 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 7/23/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/19/2025 Partial Approval JON MCHUGH
Special/Order Compliance 8/19/2025 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 8/22/2025 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 8/25/2025 Partial Approval JON MCHUGH
Footing/Foundation/Slab 8/25/2025 Partial Approval JON MCHUGH
PLUMBING-Rough 9/11/2025 Partial Approval MORRIS JACKSON
Underground Mechanical 9/11/2025 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 9/26/2025 Approved JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/26/2025 Approved JON MCHUGH
Footing/Foundation/Slab 9/26/2025 Approved JON MCHUGH
Deputy Steel/Welding 10/7/2025 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval JON MCHUGH
Underground Mechanical 1/21/2026 Corrections Issued JON MCHUGH
HVAC-Rough 2/20/2026 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 3/16/2026 Partial Approval JON MCHUGH
PLUMBING-Rough 3/20/2026 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 3/27/2026 Approved JON MCHUGH
BUILDING-Rough-Frame 4/17/2026 Approved JON MCHUGH
Green Building Rough 4/17/2026 Approved JON MCHUGH
Verify Sprinkler Sign Off 4/17/2026 Approved JON MCHUGH
Insulation 5/1/2026 Approved JON MCHUGH
Interior/Exterior Lathing 5/1/2026 Partial Approval JON MCHUGH
Drywall Nailing 5/27/2026 Approved JON MCHUGH