1744 1/2 W 36TH PL 90018

Certificate Information: 1744 1/2 W 36TH PL 90018

Application / Permit
24010-10000-04578
Plan Check / Job No.
B24LA30316
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 ALEC MOUSAKHANIAN
Corrections Issued 11/18/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 2/19/2025 PINANK PATEL
Plan Check Approved 3/11/2025 ALEC MOUSAKHANIAN
Issued 5/6/2025 APPLICANT
CofO in Progress 10/13/2025 SABAS ALONSO
Permit Finaled 10/17/2025 DEROLD HAUFF
CofO Issued 10/17/2025 DEROLD HAUFF
Permit Finaled 10/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Flood clearance Cleared 12/17/2024 SAMSON WONG
Eng Process Fee Ord 176,300 Cleared 12/26/2024 DAVID LOPEZ
Sewer availability Cleared 12/26/2024 DAVID LOPEZ
Address approval Cleared 1/22/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 1/22/2025 DAVID LOPEZ
Construction near power lines Cleared 3/5/2025 RIDWAN HARDY
Construction within easement Cleared 3/5/2025 RIDWAN HARDY

Contact Information

Contractor Phoebe Construction; Lic. No.: 1070728-B       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/2/2025 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 6/11/2025 Partial Approval SABAS ALONSO
Sewer 6/11/2025 Approved SABAS ALONSO
Underground Mechanical 6/11/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 6/16/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 6/24/2025 Approved SABAS ALONSO
Underground Mechanical 6/24/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Partial Approval BARRY HACHE
Green Building Rough 7/7/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 7/9/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 7/9/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 7/9/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 7/11/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 7/11/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Approved SABAS ALONSO
Green Building Rough 7/11/2025 Approved SABAS ALONSO
HVAC-Rough 7/11/2025 Approved SABAS ALONSO
PLUMBING-Rough 7/11/2025 Approved SABAS ALONSO
Underground Mechanical 7/11/2025 Partial Approval SABAS ALONSO
Insulation 7/15/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 7/15/2025 Partial Approval SABAS ALONSO
Drywall Nailing 7/21/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 7/21/2025 Approved SABAS ALONSO
Shower Pan 7/21/2025 Approved SABAS ALONSO
Underground Mechanical 7/21/2025 Approved SABAS ALONSO
Final 9/17/2025 Corrections Issued SABAS ALONSO
Green Building Final 9/17/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 9/17/2025 Not Ready for Inspection SABAS ALONSO
Final 10/3/2025 Conditional Approval BRENDAN MORELLI
Smoke Detectors 10/3/2025 Approved BRENDAN MORELLI
Final 10/10/2025 OK to Issue CofO SABAS ALONSO