119 E 103RD ST 90003
Certificate Information: 119 E 103RD ST 90003
- Application / Permit
- 24010-10000-04523
- Plan Check / Job No.
- B24LA29460
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) AND (e) AT REAR OF LOT. ALL CONSTRUCTION PER WFPP. SOLAR INSTALLATION REQUIRED TO MEET (2.18KW) PER TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | VIVIAN LAO |
| Corrections Issued | 11/13/2024 | VIVIAN LAO |
| Quality Review Completed | 11/15/2024 | KEN GILL |
| Building Plans Picked Up | 11/18/2024 | APPLICANT |
| Applicant returned to address corrections | 1/2/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 2/25/2025 | VIVIAN LAO |
| Applicant returned to address corrections | 3/11/2025 | VIVIAN LAO |
| Plan Check Approved | 4/24/2025 | VIVIAN LAO |
| Issued | 4/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/3/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 4/22/2025 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/20/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/23/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/11/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/22/2025 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 7/22/2025 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 8/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 8/12/2025 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 11/4/2025 | No Access for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/6/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/12/2025 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/17/2025 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/11/2025 | Partial Approval | ARTHUR NEGRETE |
| Drywall Nailing | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 12/11/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 12/11/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/24/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 12/24/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 12/24/2025 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Drywall Nailing | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 12/30/2025 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 12/30/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 1/5/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/26/2026 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 1/26/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/9/2026 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 3/9/2026 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/17/2026 | Corrections Issued | BEN MOLSTAD |
| Insulation | 4/17/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/24/2026 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 4/24/2026 | Corrections Issued | BEN MOLSTAD |
| Insulation | 4/24/2026 | Not Ready for Inspection | BEN MOLSTAD |