255 S CITRUS AVE 90036
Certificate Information: 255 S CITRUS AVE 90036
- Application / Permit
- 24010-10000-04474
- Plan Check / Job No.
- B24LA28786
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New 2 story detached ADU PER STATE LAW GCS 65852.2(e)(1)(B) 1 OF 2
- Permit Issued
- Issued on 5/23/2025
- Issuing Office
- Current Status
- Issued on 5/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | KHUONG TRUONG |
| Corrections Issued | 11/5/2024 | KHUONG TRUONG |
| Quality Review Completed | 11/12/2024 | GARO TELMI |
| Applicant returned to address corrections | 5/14/2025 | KHUONG TRUONG |
| Plan Check Approved | 5/22/2025 | KHUONG TRUONG |
| Issued | 5/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | CELINA MORENO |
| Sewer availability | Cleared | 11/26/2024 | CELINA MORENO |
| Historic monument | Cleared | 12/10/2024 | RAFAEL FONTES |
| Construction near power lines | Cleared | 1/8/2025 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 7/16/2025 | Conditional Approval | RONNIE MINDANAO |
| Special/Order Compliance | 7/16/2025 | Corrections Issued | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/31/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 7/31/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 7/31/2025 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 8/4/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/4/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 8/4/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Partial Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 9/12/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Conditional Approval | JOSH MEISTER |
| Special/Order Compliance | 10/21/2025 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 11/5/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/5/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 11/5/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/5/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 11/5/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/7/2025 | Conditional Approval | RONNIE MINDANAO |
| Green Building Rough | 11/7/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 11/7/2025 | Approved | RONNIE MINDANAO |
| Insulation | 11/13/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 11/19/2025 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 11/19/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 11/24/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/24/2025 | Approved | RONNIE MINDANAO |
| Sewer | 12/10/2025 | Approved | JEFFREY MEAD |