255 S CITRUS AVE 90036

Certificate Information: 255 S CITRUS AVE 90036

Application / Permit
24010-10000-04474
Plan Check / Job No.
B24LA28786
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. New 2 story detached ADU PER STATE LAW GCS 65852.2(e)(1)(B) 1 OF 2
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
Issued on 5/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 KHUONG TRUONG
Corrections Issued 11/5/2024 KHUONG TRUONG
Quality Review Completed 11/12/2024 GARO TELMI
Applicant returned to address corrections 5/14/2025 KHUONG TRUONG
Plan Check Approved 5/22/2025 KHUONG TRUONG
Issued 5/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/22/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 11/22/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/26/2024 CELINA MORENO
Sewer availability Cleared 11/26/2024 CELINA MORENO
Historic monument Cleared 12/10/2024 RAFAEL FONTES
Construction near power lines Cleared 1/8/2025 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Butel Construction Inc; Lic. No.: 852273-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 7/16/2025 Conditional Approval RONNIE MINDANAO
Special/Order Compliance 7/16/2025 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 7/31/2025 Corrections Issued RONNIE MINDANAO
METHANE-Barrier 7/31/2025 Approved RONNIE MINDANAO
METHANE-Subgrade 7/31/2025 Approved RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 8/4/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 8/4/2025 Approved RONNIE MINDANAO
PLUMBING-Rough 8/4/2025 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Partial Approval RONNIE MINDANAO
Deputy Wood Construction 9/12/2025 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Conditional Approval JOSH MEISTER
Special/Order Compliance 10/21/2025 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 11/5/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 11/5/2025 Approved RONNIE MINDANAO
HVAC-Rough 11/5/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/5/2025 Approved RONNIE MINDANAO
PLUMBING-Rough 11/5/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 11/7/2025 Conditional Approval RONNIE MINDANAO
Green Building Rough 11/7/2025 Approved RONNIE MINDANAO
METHANE-Rough 11/7/2025 Approved RONNIE MINDANAO
Insulation 11/13/2025 Approved RONNIE MINDANAO
Drywall Nailing 11/19/2025 Corrections Issued RONNIE MINDANAO
Shower Pan 11/19/2025 Approved RONNIE MINDANAO
Drywall Nailing 11/24/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/24/2025 Approved RONNIE MINDANAO
Sewer 12/10/2025 Approved JEFFREY MEAD