4838 N NORWICH AVE 91403

Certificate Information: 4838 N NORWICH AVE 91403

Application / Permit
24010-10000-04429
Plan Check / Job No.
B24LA28026
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: New detached ADU (750 SF) per GC 66323(a)(2). All work per engineer.
Permit Issued
Issued on 3/7/2025
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2024 APPLICANT
Assigned to Plan Check Engineer 10/23/2024 DANIEL SMILEY
Corrections Issued 10/24/2024 DANIEL SMILEY
Applicant returned to address corrections 1/29/2025 DANIEL SMILEY
Applicant returned to address corrections 2/5/2025 LAWRENCE QUIRANTE
Plan Check Approved 2/8/2025 NEHEMIAS RAMOS
Issued 3/7/2025 APPLICANT
CofO in Progress 11/5/2025 JACK KARGODORIAN
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/29/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/29/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/29/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/30/2024 LEE GUILBEAUX
Sewer availability Cleared 10/30/2024 LEE GUILBEAUX
Construction near power lines Cleared 1/22/2025 RIDWAN HARDY
Construction within easement Cleared 1/22/2025 RIDWAN HARDY

Contact Information

Contractor Vando Construction; Lic. No.: 1122029-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/25/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 3/27/2025 Approved JACK KARGODORIAN
Deputy Other (see comments) 4/2/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved JACK KARGODORIAN
Green Building Rough 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 4/3/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 4/11/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 4/11/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 4/24/2025 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 4/24/2025 Partial Approval JACK KARGODORIAN
MERV13>=Rough 4/24/2025 Approved JACK KARGODORIAN
HVAC-Rough 6/4/2025 Approved JACK KARGODORIAN
Insulation 6/4/2025 Corrections Issued JACK KARGODORIAN
Drywall Nailing 6/9/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/30/2025 Approved JACK KARGODORIAN
Sewer 7/17/2025 Not Ready for Inspection MICHAEL CORTEZ
Sewer 7/18/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 7/21/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 9/16/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 9/18/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/30/2025 Approved JACK KARGODORIAN
Final 10/30/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 10/30/2025 Approved JACK KARGODORIAN
Green Building Rough 10/30/2025 Approved JACK KARGODORIAN
MERV13>=Final 10/30/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 10/30/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 10/30/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 10/30/2025 Approved JACK KARGODORIAN
Final 11/4/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 11/4/2025 Approved JACK KARGODORIAN