313-313 1/2 E 59TH PL 90003
Certificate Information: 313-313 1/2 E 59TH PL 90003
- Application / Permit
- 24010-10000-04425
- Plan Check / Job No.
- B24VN19230
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- [ePlan] NEW 2-STORY DUPLEX (FRONT LOT) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 4/21/2025
- Issuing Office
- Current Status
- CofO Issued on 12/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/21/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/30/2024 | TU HUA |
| Applicant returned to address corrections | 3/20/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/2/2025 | MAHNAZ NOURHASHEMI |
| Issued | 4/21/2025 | APPLICANT |
| CofO in Progress | 12/23/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/28/2025 | DEROLD HAUFF |
| CofO Issued | 12/28/2025 | DEROLD HAUFF |
| Permit Finaled | 12/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 11/12/2024 | JULIE LIEU |
| Low Impact Development (LID) | Cleared | 11/19/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | ADRIAN SANCHEZ |
| Address approval | Cleared | 12/3/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/3/2024 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 12/3/2024 | MIGUEL ORNELAS |
| Frnt yard landscape/Water mgmt | Cleared | 12/23/2024 | DALIA MOKAYED |
| Redevelopment Project Area | Cleared | 1/16/2025 | YASMINE BASHIRI |
| Permit | Cleared | 2/13/2025 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/18/2025 | FRANK GOMEZ |
| Highway dedication | Cleared | 2/21/2025 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/30/2025 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 8/1/2025 | Partial Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/8/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/10/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 11/10/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/10/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 12/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/23/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 12/23/2025 | Approved | ALEJANDRO DE ARTOLA |