1159 S RODEO DR 90035

Certificate Information: 1159 S RODEO DR 90035

Application / Permit
24010-10000-04422
Plan Check / Job No.
B24LA27968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] NEW 2-STORY SFD OVER BASEMENT WITH ATTACHED 2-CAR GARAGE AND RECREATION ROOM -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 6/20/2025
Issuing Office
Current Status
Issued on 6/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 MAHNAZ NOURHASHEMI
Corrections Issued 11/7/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 11/20/2024 TU HUA
Applicant returned to address corrections 4/17/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 5/23/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 6/4/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 6/18/2025 MAHNAZ NOURHASHEMI
Issued 6/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/12/2024 LIAM ODONOVAN
Permit Cleared 12/12/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 12/27/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 12/27/2024 VLADIMIR ARUTYUNYAN
Hydrant and Access approval Cleared 12/30/2024 JOHN CONNEALLY
Specific Plan Cleared 2/5/2025 JOSHUA JONES
Low Impact Development (LID) Cleared 2/7/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 3/14/2025 LIAM ODONOVAN
Trees in Parkway Cleared 4/14/2025 ADALBERTO VERA
Grading Pre-Inspection Cleared 5/23/2025 MAHNAZ NOURHASHEMI
GPI Written Notices Cleared 6/13/2025 MAHNAZ NOURHASHEMI

Contact Information

Contractor Harari Construction Inc; Lic. No.: 1017539-B       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/18/2025 Partial Approval ASHLEY THOMPSON
Underground Mechanical 8/18/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 8/25/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 8/25/2025 Partial Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 9/22/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 9/22/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Barrier 9/22/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Subgrade 9/22/2025 Not Ready for Inspection ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 9/23/2025 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/3/2025 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/4/2026 Approved WILBER ROSALES
METHANE-Barrier 3/4/2026 Approved WILBER ROSALES
METHANE-Subgrade 3/4/2026 Approved WILBER ROSALES
PLUMBING-Rough 3/31/2026 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/13/2026 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/20/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 5/4/2026 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/15/2026 Corrections Issued ASHLEY THOMPSON