3218-3220 W LARISSA DR 90026
Certificate Information: 3218-3220 W LARISSA DR 90026
- Application / Permit
- 24010-10000-04331
- Plan Check / Job No.
- B24LA27129
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan: Addition of laundry room, attached storage, and attached patio with deck to existing 2-story duplex
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- CofO Issued on 7/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | KHEDER ALRAZAA |
| Corrections Issued | 12/10/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 12/10/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 1/29/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 2/21/2025 | KHEDER ALRAZAA |
| Issued | 3/13/2025 | APPLICANT |
| CofO in Progress | 7/14/2025 | FREDDIE RIVERA |
| Permit Finaled | 7/16/2025 | DEROLD HAUFF |
| CofO Issued | 7/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/21/2024 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 1/30/2025 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Landmark Building, Inc; Lic. No.: 967613-B | 4636 1/2 CLARISSA AVE LOS ANGELES, CA 90027 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/16/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/16/2025 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 5/16/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/2/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/2/2025 | Approved | FREDDIE RIVERA |
| Gas Test | 6/2/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/2/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/2/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/6/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 6/6/2025 | Approved | ALEX COLIN |
| Final | 6/30/2025 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 6/30/2025 | Approved | WILLIAM SIERRA |
| Green Building Final | 6/30/2025 | Approved | WILLIAM SIERRA |
| Smoke Detectors | 6/30/2025 | Approved | WILLIAM SIERRA |
| Final | 7/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 7/7/2025 | OK to Issue CofO | FREDDIE RIVERA |