345 N MADISON AVE 1-148 90004

Certificate Information: 345 N MADISON AVE 1-148 90004

Application / Permit
24010-10000-04311
Plan Check / Job No.
B24LA26907
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN. NEW 148 UNIT FULLY AFFORDABLE MODULAR HOUSING PROJECT COMPRISED OF 46 VLI, 100 ELI, AND 2 MGR UNITS. (6) STORY BUILDING AT OAKWOOD AND MADISON COMPRISED OF (5) STORIES OF TYPE III-A FACTORY BUILT MODULAR RESIDENTIAL UNITS ABOVE GROUND LEVEL TYPE I-A AMENITIES AND COMMUNITY SERVICES. BUILDING IS FULLY SPRINKLERED
Permit Issued
Issued on 6/27/2025
Issuing Office
Metro
Current Status
Issued on 6/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/17/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 VU NGUYEN
Assigned to Zoning Architect 10/17/2024 KAITA SAITO
Corrections Issued 10/21/2024 VU NGUYEN
Quality Review Completed 10/23/2024 EUGENE BARBEAU
Applicant returned to address corrections 1/29/2025 VU NGUYEN
Applicant returned to address corrections 5/7/2025 VU NGUYEN
Plan Check Approved 6/27/2025 VU NGUYEN
Issued 6/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/16/2024 STEVE MELGAR
Highway dedication Cleared 12/14/2024 TREVOR QUAN
Historic Resource Verification Cleared 1/13/2025 LAMBERT GIESSINGER
Permit Cleared 1/13/2025 ALBERT TAM
Roof/Waste drainage to street Cleared 1/13/2025 ALBERT TAM
Hydrant and Access approval Cleared 1/27/2025 KURT CORRAL
Sewer availability Cleared 1/31/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/4/2025 TREVOR QUAN
Trees in Parkway Cleared 2/6/2025 MIGUEL ORNELAS
DAS Clearance Cleared 2/7/2025 Manuel Montufar
Low Impact Development (LID) Cleared 2/13/2025 MARTIN FRAGOSO
Green Code Cleared 5/15/2025 Manuel Montufar
DCP conditions approval Cleared 5/27/2025 OLIVIA JIN
Miscellaneous Cleared 5/29/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 5/29/2025 YASMINE BASHIRI
Bicycle Parking Cleared 6/12/2025 ARNULFO CHAMU
Miscellaneous Cleared 6/16/2025 JAZMIN ROQUE
Specific Plan Cleared 6/16/2025 JAZMIN ROQUE
Fire Marshal Fire Life Safety Cleared 6/19/2025 FIRE DEPARTMENT
Public Housing Cleared 6/20/2025 PAUL MUNZ
Building over 36-ft Cleared 6/24/2025 CALOSHA APPROVED
CPC Cleared 6/24/2025 JAZMIN ROQUE
Zoning Plan Check Cleared 6/24/2025 Manuel Montufar

Contact Information

Architect Bornstein,, Lise Michelle; Lic. No.: C30835 3573 HAYDEN AVENUE      CULVER CITY, CA 90232
Contractor Sinanian Development Inc; Lic. No.: 455273-A 18980 VENTURA BLVD 2ND FLOOR      TARZANA, CA 91356
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Risung,, Kai Magnus; Lic. No.: C92053 3936 NORTH 1100 EAST      BUHL, ID 83316

Inspector Information

No Data Available.

Pending Inspections

Excavation/Setback/Form/Re-Bar 7/24/2026    Time Frame: 12-2
Deputy Reinf. Concrete 7/24/2026   

Inspection Request History

Deputy Reinf. Concrete 1/13/2026 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/13/2026 Partial Inspection DAVID BURKHEAD
Piling/Pier/Caisson 1/13/2026 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/14/2026 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval RAFAEL CORTES
Green Building Rough 2/9/2026 Not Ready for Inspection RAFAEL CORTES
METHANE-Rough 2/9/2026 Not Ready for Inspection RAFAEL CORTES
Piling/Pier/Caisson 2/9/2026 Partial Approval RAFAEL CORTES
Reinforced Concrete Frame 2/9/2026 Partial Approval RAFAEL CORTES
Verify Sprinkler Sign Off 2/9/2026 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 2/10/2026 Partial Inspection DAVID BURKHEAD
Piling/Pier/Caisson 2/10/2026 Partial Inspection DAVID BURKHEAD
Deputy Grading 2/12/2026 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/12/2026 Not Ready for Inspection DAVID BURKHEAD
Deputy Grading 2/25/2026 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/25/2026 Partial Inspection DAVID BURKHEAD
Piling/Pier/Caisson 2/25/2026 Partial Inspection DAVID BURKHEAD
Deputy Grading 3/6/2026 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 3/6/2026 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 3/6/2026 Partial Approval RAFAEL CORTES
Piling/Pier/Caisson 3/6/2026 Partial Approval RAFAEL CORTES
Deputy Grading 3/20/2026 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 3/20/2026 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 3/20/2026 No Access for Inspection RAFAEL CORTES
Piling/Pier/Caisson 3/20/2026 Not Ready for Inspection RAFAEL CORTES
Deputy Grading 3/24/2026 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 3/24/2026 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 3/24/2026 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 3/24/2026 Not Ready for Inspection RAFAEL CORTES
METHANE-Barrier 3/24/2026 Not Ready for Inspection RAFAEL CORTES
METHANE-Subgrade 3/24/2026 Not Ready for Inspection RAFAEL CORTES
Deputy Grading 3/25/2026 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 3/25/2026 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 3/25/2026 Partial Approval RAFAEL CORTES
Deputy Grading 4/9/2026 Conditional Approval RAFAEL CORTES
Deputy Reinf. Concrete 4/9/2026 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 4/9/2026 Partial Approval RAFAEL CORTES
Piling/Pier/Caisson 4/9/2026 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 4/29/2026 Partial Approval RAFAEL CORTES
METHANE-Subgrade 5/5/2026 Not Ready for Inspection RAFAEL CORTES
Piling/Pier/Caisson 5/5/2026 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 5/11/2026 No Access for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 5/14/2026 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/26/2026 Partial Approval RAFAEL CORTES
Special/Order Compliance 7/10/2026 No Access for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 7/20/2026 Not Ready for Inspection RAFAEL CORTES