8404-8404 1/2 W 4TH ST 90048
Certificate Information: 8404-8404 1/2 W 4TH ST 90048
- Application / Permit
- 24010-10000-04281
- Plan Check / Job No.
- B24LA26644
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO STORY BUILDING ( TWO ACCESSORY DWELLING UNITS) PER CA GOVT CODE 65852.2(e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 11/5/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/8/2024 | KEN GILL |
| Building Plans Picked Up | 11/8/2024 | APPLICANT |
| Plan Check Approved | 7/17/2025 | SERGIO GUTIERREZ |
| Issued | 7/31/2025 | APPLICANT |
| CofO in Progress | 4/21/2026 | WILBER ROSALES |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
| CofO Issued | 4/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction within easement | Cleared | 1/7/2025 | RIDWAN HARDY |
| Address approval | Cleared | 1/24/2025 | CELINA MORENO |
| CPC | Cleared | 1/24/2025 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 1/24/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/28/2025 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2025 | Corrections Issued | EVAN COOPER |
| METHANE-Subgrade | 8/25/2025 | Partial Approval | EVAN COOPER |
| Sewer | 8/27/2025 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 8/27/2025 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/9/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 9/9/2025 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 9/9/2025 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 9/9/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 9/9/2025 | Partial Approval | EVAN COOPER |
| Sewer | 9/18/2025 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 9/18/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 9/19/2025 | Partial Approval | EVAN COOPER |
| Sewer | 9/19/2025 | Not Ready for Inspection | EVAN COOPER |
| Deputy Methane Barrier | 10/6/2025 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/9/2025 | Approved | EVAN COOPER |
| METHANE-Barrier | 10/9/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 10/9/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2025 | Partial Approval | EVAN COOPER |
| Wood Frame | 10/21/2025 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 10/30/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 11/12/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 11/12/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 11/17/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 11/17/2025 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 11/17/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 11/17/2025 | Approved | EVAN COOPER |
| Shower Pan | 11/17/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 11/19/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 11/19/2025 | Approved | EVAN COOPER |
| Deputy Methane Barrier | 11/25/2025 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/2/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | EVAN COOPER |
| Green Building Rough | 12/2/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 12/2/2025 | Approved | EVAN COOPER |
| Wood Frame | 12/2/2025 | Approved | EVAN COOPER |
| Insulation | 12/5/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/5/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 12/24/2025 | Approved | EVAN COOPER |
| Special/Order Compliance | 12/24/2025 | Corrections Issued | EVAN COOPER |
| Sewer | 1/29/2026 | Corrections Issued | WILBER ROSALES |
| Underground Mechanical | 1/29/2026 | Corrections Issued | WILBER ROSALES |
| Sewer | 2/2/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 2/2/2026 | Partial Approval | WILBER ROSALES |
| Underground Mechanical | 3/11/2026 | Partial Approval | WILBER ROSALES |
| Underground Mechanical | 3/16/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 3/20/2026 | Approved | WILBER ROSALES |
| Final | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | WILBER ROSALES |
| Service/Power Release | 3/20/2026 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 3/20/2026 | Approved | WILBER ROSALES |
| Underground Mechanical | 3/20/2026 | Corrections Issued | WILBER ROSALES |
| Final | 3/25/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 3/25/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 3/25/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 3/25/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Not Ready | WILBER ROSALES |
| Service/Power Release | 3/25/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 3/25/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 3/31/2026 | Approved | WILBER ROSALES |
| Final | 4/17/2026 | OK to Issue CofO | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 4/17/2026 | Approved | WILBER ROSALES |