5022 N WOODLEY AVE 91436

Certificate Information: 5022 N WOODLEY AVE 91436

Application / Permit
24010-10000-04239
Plan Check / Job No.
B24LA26105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan New 2-story single family dwelling with attached 3-car garage fully sprinklered NFPA 13D through out
Permit Issued
Issued on 7/24/2025
Issuing Office
Current Status
Issued on 7/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 JAD BASMA
Corrections Issued 10/11/2024 JAD BASMA
Quality Review Completed 10/16/2024 PRANITA SHAH
Applicant returned to address corrections 12/18/2024 JAD BASMA
Applicant returned to address corrections 7/15/2025 JAD BASMA
Plan Check Approved 7/24/2025 JAD BASMA
Plan Check Approved 7/24/2025 JAD BASMA
Issued 7/24/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/22/2024 BIAINA HARITUNIAN
ZA Case Cleared 10/28/2024 ALEX VELA
Trees in Parkway Cleared 11/6/2024 MIGUEL ORNELAS
Hydrant and Access approval Cleared 2/3/2025 KURT CORRAL
Low Impact Development (LID) Cleared 7/16/2025 LUIS LUVANO
Permit Cleared 7/17/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 7/17/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/15/2025 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 8/20/2025 Partial Approval ARUTYUN MADATYAN
Underground Mechanical 8/20/2025 Partial Approval ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 9/3/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 9/3/2025 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 9/4/2025 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/4/2025 Approved THOMAS FINNILA
Deputy Reinf. Concrete 9/5/2025 Conditional Approval HENRY KIM
Deputy Drilled-In Anchors 9/22/2025 Approved SEAN WIRCH
Deputy Wood Construction 9/22/2025 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval MORRIS JACKSON
Deputy Wood Construction 10/28/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 11/4/2025 Approved JEFFREY HARTLINE
HVAC-Rough 11/26/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Order to Comply Issued JOHN KIDWELL
HVAC-Rough 12/9/2025 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 12/11/2025 Partial Approval JON MCHUGH
HVAC-Rough 12/29/2025 Approved SEAN WIRCH
BUILDING-Rough-Frame 12/31/2025 Approved SEAN WIRCH
Green Building Rough 12/31/2025 Approved SEAN WIRCH
Verify Sprinkler Sign Off 12/31/2025 Approved SEAN WIRCH
Shower Pan 1/8/2026 Approved THOMAS FINNILA
Insulation 1/20/2026 Approved MORRIS JACKSON
Interior/Exterior Lathing 1/20/2026 Partial Approval MORRIS JACKSON
Drywall Nailing 1/26/2026 Approved ROBERT GOLD
Interior/Exterior Lathing 2/6/2026 Approved THOMAS FINNILA
ELECTRICAL-Rough 6/29/2026 Approved THOMAS FINNILA