2406 N BIRKDALE ST 90031
Certificate Information: 2406 N BIRKDALE ST 90031
- Application / Permit
- 24010-10000-04206
- Plan Check / Job No.
- B24LA25878
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ADU WITH OPEN ROOF DECK PER GC 66323(a)(2)
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2024 | SERGIO MUNIZ |
| Corrections Issued | 10/10/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 1/30/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/27/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/13/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/15/2025 | SERGIO MUNIZ |
| Plan Check Approved | 4/21/2025 | SERGIO MUNIZ |
| Issued | 4/22/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
| CofO Issued | 5/28/2026 | DEROLD HAUFF |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/11/2024 | JILVER MAZARIEGOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 10/16/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 10/16/2024 | JILVER MAZARIEGOS |
| Miscellaneous | Cleared | 12/5/2024 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 6/3/2025 | Partial Inspection | OSVALDO PARAMO |
| Underground Mechanical | 6/3/2025 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/12/2025 | Approved | HAMIK HARTOUNIAN |
| Sewer | 6/24/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/24/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/24/2025 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/29/2025 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 9/29/2025 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 10/2/2025 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/2/2025 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/3/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 10/9/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 10/9/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/9/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/9/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/31/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 10/31/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/31/2025 | Partial Approval | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/31/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/31/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/10/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/10/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/10/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 11/13/2025 | Approved | DEVON JACKSON |
| Shower Pan | 11/13/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 11/19/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 11/20/2025 | Approved | DEVON JACKSON |
| Final | 5/26/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 5/26/2026 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 5/26/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 5/26/2026 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/26/2026 | Approved | HAMIK HARTOUNIAN |