1239 S WILTON PL 90019

Certificate Information: 1239 S WILTON PL 90019

Application / Permit
24010-10000-04192
Plan Check / Job No.
B24LA25746
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New 2 story detached ADU to be attached to existing 2 car garage. ADU per LAMC 12.22 A.33 (c) and (d)
Permit Issued
Issued on 8/8/2025
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 MARCELA FRANQUEZ
Corrections Issued 10/23/2024 MARCELA FRANQUEZ
Quality Review Completed 10/31/2024 TU HUA
Applicant returned to address corrections 1/23/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 6/13/2025 MARCELA FRANQUEZ
Plan Check Approved 7/14/2025 MARCELA FRANQUEZ
Issued 8/8/2025 APPLICANT
CofO in Progress 4/13/2026 JUSTIN HAWLEY
No Progress 4/14/2026 DEROLD HAUFF
CofO in Progress 4/14/2026 DEROLD HAUFF
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/10/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 1/10/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 1/14/2025 CARLOS AGUILERA
Sewer availability Cleared 1/14/2025 CARLOS AGUILERA
CPC Cleared 1/15/2025 MICAELA TORRES-GIL
HPOZ Cleared 1/15/2025 MICAELA TORRES-GIL
ZI Cleared 1/15/2025 MICAELA TORRES-GIL

Contact Information

Contractor Ubcon Inc; Lic. No.: 1058343-B       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28531 PALOS VERDES DR EAST      RANCHO PALOS VERDES, CA 90275

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/3/2025 Conditional Approval WILLIAM SIERRA
Footing/Foundation/Slab 9/4/2025 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 9/4/2025 Approved ALIZAH MAYAGOITIA
METHANE-Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 9/4/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 9/4/2025 Partial Approval ALIZAH MAYAGOITIA
Sewer 9/4/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Partial Approval WILLIAM SIERRA
Deputy Wood Construction 10/6/2025 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 11/7/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 11/14/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 11/20/2025 Corrections Issued WILLIAM SIERRA
Green Building Rough 11/20/2025 Approved WILLIAM SIERRA
HVAC-Rough 11/20/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 11/20/2025 Approved WILLIAM SIERRA
Insulation 12/5/2025 Approved DEVON JACKSON
BUILDING-Rough-Frame 12/9/2025 Approved DEVON JACKSON
Drywall Nailing 12/16/2025 Corrections Issued WILLIAM SIERRA
Drywall Nailing 12/22/2025 Approved ALEX COLIN
Service/Power Release 2/13/2026 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Final 3/27/2026 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 3/27/2026 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Final 3/27/2026 Corrections Issued WILLIAM SIERRA
Service/Power Release 3/27/2026 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Final 4/9/2026 Approved WILLIAM SIERRA
Final 4/9/2026 Corrections Issued WILLIAM SIERRA
Green Building Final 4/9/2026 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 4/9/2026 Approved WILLIAM SIERRA
PLUMBING-Final 4/9/2026 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Not Required WILLIAM SIERRA
Smoke Detectors 4/9/2026 Approved WILLIAM SIERRA
Final 4/13/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 4/13/2026 Approved JUSTIN HAWLEY
Service/Power Release 4/13/2026 Approved JUSTIN HAWLEY