2721-2721 1/2 E MARENGO ST 90033

Certificate Information: 2721-2721 1/2 E MARENGO ST 90033

Application / Permit
24010-10000-04187
Plan Check / Job No.
B24LA25672
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*E-plan.* New two-story duplex. < NFPA 13D fire sprinklers REQ Thru-out BLDG. >
Permit Issued
Issued on 5/5/2025
Issuing Office
Current Status
Issued on 5/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/3/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 JOHNNY WU
Corrections Issued 1/2/2025 HUAN LE
Quality Review Completed 1/10/2025 PRANITA SHAH
Applicant returned to address corrections 2/14/2025 HUAN LE
Applicant returned to address corrections 3/14/2025 HUAN LE
Plan Check Approved 5/1/2025 HUAN LE
Issued 5/5/2025 APPLICANT

Permit Application Clearance Information

Clean Up Green Up Cleared 1/27/2025 JAZMIN ROQUE
Address approval Cleared 2/20/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 2/20/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/28/2025 JEANIE LAM
Sewer availability Cleared 2/28/2025 BIAINA HARITUNIAN
Frnt yard landscape/Water mgmt Cleared 3/4/2025 JASON CHAN
Hydrant and Access approval Cleared 3/7/2025 JERRY KAO
Highway dedication Cleared 4/30/2025 JEANIE LAM
GPI Written Notices Cleared 5/1/2025 HUAN LE
Grading Pre-Inspection Cleared 5/1/2025 HUAN LE

Contact Information

Contractor Green Light Construction Inc; Lic. No.: 1065833-B       ,
Engineer Mirpoor,, Waheed Ahmad; Lic. No.: C94801 555 ROSEWOOD AVE   APT#308    CAMARILLO, CA 93010

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/6/2025 No Access for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 6/10/2025 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/3/2025 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 7/3/2025 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 7/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 7/11/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/17/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/22/2025 Not Ready for Inspection JOHN QUINTANILLA
Pre-Inspection 7/22/2025 Not Ready for Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 7/24/2025 Corrections Issued OSVALDO PARAMO
Pre-Inspection 7/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 7/28/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/28/2025 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Rough 10/28/2025 Corrections Issued DAVID WILLIAMS
MERV13>=Rough 10/28/2025 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Rough 10/28/2025 Corrections Issued DAVID WILLIAMS
Verify Sprinkler Sign Off 10/28/2025 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Rough 10/29/2025 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 10/29/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/17/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/17/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 11/17/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 12/2/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 12/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 3/3/2026 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/17/2026 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/17/2026 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/17/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 4/17/2026 Corrections Issued ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 4/17/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/24/2026 No Access for Inspection DAVID WILLIAMS
MERV13>=Rough 4/24/2026 No Access for Inspection DAVID WILLIAMS
PLUMBING-Rough 4/24/2026 No Access for Inspection DAVID WILLIAMS
Verify Sprinkler Sign Off 4/24/2026 No Access for Inspection DAVID WILLIAMS
BUILDING-Rough-Frame 5/4/2026 Not Ready for Inspection RONNIE MEDINA
MERV13>=Rough 5/4/2026 Approved RONNIE MEDINA
Rough-Elec/Plmb/HVAC 5/4/2026 Not Ready for Inspection RONNIE MEDINA
Verify Sprinkler Sign Off 5/4/2026 Not Ready for Inspection RONNIE MEDINA
BUILDING-Rough-Frame 5/7/2026 Approved JOSH MEISTER
PLUMBING-Rough 5/7/2026 Approved JOSH MEISTER
Verify Sprinkler Sign Off 5/7/2026 Approved JOSH MEISTER
Insulation 5/11/2026 Approved OSVALDO PARAMO
Drywall Nailing 5/14/2026 Approved OSVALDO PARAMO
Shower Pan 7/6/2026 Approved OSVALDO PARAMO
Structural Steel Frame 7/6/2026 Approved OSVALDO PARAMO