NEW 399 SQ.FT DETACHED 1 STORY ADU WORK PER WFPP
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/8/2024 JOSEPH RAFOLS
Corrections Issued 10/8/2024 JOSEPH RAFOLS
Building Plans Picked Up 10/16/2024 APPLICANT
Applicant returned to address corrections 10/24/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 10/30/2024 ZAW HAN
Plan Check Approved 10/31/2024 EDWIN MARTINEZ
Issued 11/7/2024 APPLICANT
CofO in Progress 10/28/2025 ALIZAH MAYAGOITIA
Permit Finaled 10/29/2025 DEROLD HAUFF
CofO Issued 10/29/2025 DEROLD HAUFF
Permit Finaled 10/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 10/9/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/9/2024 ADRIAN SANCHEZ
Sewer availability Cleared 10/9/2024 JUSTIN BICOL
Clean Up Green Up Cleared 10/11/2024 DAVID URITA
Grading Pre-Inspection Cleared 10/11/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2025 No Access for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/10/2025 Approved ALIZAH MAYAGOITIA
Underground Mechanical 5/13/2025 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 5/14/2025 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/23/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/2/2025 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval LILIANA PORTILLO
HVAC-Rough 7/2/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/2/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/11/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 7/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 7/11/2025 Corrections Issued ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 7/11/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/15/2025 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 7/15/2025 Approved DAVID WILLIAMS
Green Building Rough 7/15/2025 Approved DAVID WILLIAMS
HVAC-Rough 7/15/2025 Not Ready for Inspection DAVID WILLIAMS
Verify Sprinkler Sign Off 7/15/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 7/21/2025 Approved JUSTIN HAWLEY
HVAC-Rough 7/21/2025 Approved JUSTIN HAWLEY
Insulation 8/6/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 8/6/2025 Approved JOHN QUINTANILLA
Drywall Nailing 8/13/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/19/2025 Approved ANTHONY RAMOS
Underground Mechanical 9/19/2025 Partial Approval ANTHONY RAMOS
Sewer 9/26/2025 Approved ANTHONY RAMOS
Underground Mechanical 9/26/2025 Partial Approval ANTHONY RAMOS
ELECTRICAL-Final 10/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 10/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 10/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 10/6/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/6/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 10/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 10/6/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/16/2025 Corrections Issued LILIANA PORTILLO
Final 10/16/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 10/16/2025 Approved LILIANA PORTILLO
HVAC-Final 10/16/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Not Required LILIANA PORTILLO
Service/Power Release 10/16/2025 Not Ready for Inspection LILIANA PORTILLO
Final 10/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 10/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 10/27/2025 Partial Approval ALIZAH MAYAGOITIA
Service/Power Release 10/27/2025 Approved ALIZAH MAYAGOITIA
Final 10/28/2025 OK to Issue CofO ALIZAH MAYAGOITIA