1013 N SYCAMORE AVE 90038
Certificate Information: 1013 N SYCAMORE AVE 90038
- Application / Permit
- 24010-10000-04174
- Plan Check / Job No.
- B24LA25530
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan** New 2-story office building ; CORE AND SHELL ONLY *** CONSTRUCTION SHALL NOT COMMENCE WITHOUT CALOSHA PERMIT
- Permit Issued
- Issued on 8/5/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 10/24/2024 | JASON BRAVO |
| Corrections Issued | 10/31/2024 | KESETE HAREGOT |
| Quality Review Completed | 11/5/2024 | RODOLFO ARIAS |
| Plan Check Approved | 7/29/2025 | SINA KHOSRAVI |
| Issued | 8/5/2025 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 12/10/2024 | CHRISTINA BRACO |
| Bicycle Parking | Cleared | 1/27/2025 | MARK REYES |
| Permit | Cleared | 1/28/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | CHRISTINA BRACO |
| CPC | Cleared | 2/14/2025 | JASON CHAN |
| Miscellaneous | Cleared | 2/14/2025 | JASON CHAN |
| Address approval | Cleared | 2/27/2025 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 4/22/2025 | KURT CORRAL |
| Sewer availability | Cleared | 5/27/2025 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 6/4/2025 | MARCO SANCHEZ |
| DAS Clearance | Cleared | 6/5/2025 | KESETE HAREGOT |
| Green Code | Cleared | 6/9/2025 | KESETE HAREGOT |
| Roof/Waste drainage to street | Cleared | 6/9/2025 | WALLIE JONG |
| Zoning Plan Check | Cleared | 6/18/2025 | Eugene Barbeau |
Contact Information
| Architect | Murnane,, R Mcshane; Lic. No.: C34176 | 2898 ROWENA AVENUE UNIT 102 LOS ANGELES, CA 90039 |
| Contractor | Owner-Builder | , |
| Engineer | Berliner,, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | John,, Benjamin Morgan; Lic. No.: S6932 | 1968 SE MULBERRY AVE PORTLAND, OR 97214 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/7/2025 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 8/25/2025 | Partial Approval | JOEY BUCHANAN |
| Deputy Other (see comments) | 9/8/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/8/2025 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 9/8/2025 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 10/23/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 11/4/2025 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 11/4/2025 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 11/4/2025 | Partial Approval | SCOTT SOBEL |
| Deputy Reinf. Masonry | 11/10/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 11/12/2025 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 11/12/2025 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/12/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 11/26/2025 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/26/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 11/26/2025 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/26/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 12/3/2025 | Partial Approval | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 12/12/2025 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 1/21/2026 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 2/19/2026 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Partial Approval | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Partial Approval | MARTIN TAVITIAN |
| Wood Frame | 5/29/2026 | Partial Approval | MARTIN TAVITIAN |