1450 1/2 N TREMONT ST 90033
Certificate Information: 1450 1/2 N TREMONT ST 90033
- Application / Permit
- 24010-10000-04173
- Plan Check / Job No.
- B24LA25517
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: New 1-story 476 SF DETACHED PROPOSED ADU Per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2024 | ALEXANDER JOO |
| Corrections Issued | 10/8/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 11/7/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 11/23/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 11/25/2024 | ZAW HAN |
| Plan Check Approved | 12/16/2024 | ZAW HAN |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 3/31/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
| CofO Issued | 4/2/2026 | DEROLD HAUFF |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/12/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 11/13/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 11/15/2024 | LANNY MERRICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sparks,, David Michael; Lic. No.: C65739 | 2996 SLY FOX CIRCLE ELIZABETH, CO 80107 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 2/10/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/28/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/30/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 5/1/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 5/1/2025 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 5/8/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/7/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/24/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 3/24/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Service/Power Release | 3/24/2026 | Approved | RONNIE MEDINA |
| Final | 3/26/2026 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 3/31/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |