1450 1/2 N TREMONT ST 90033

Certificate Information: 1450 1/2 N TREMONT ST 90033

Application / Permit
24010-10000-04173
Plan Check / Job No.
B24LA25517
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: New 1-story 476 SF DETACHED PROPOSED ADU Per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/7/2024 ALEXANDER JOO
Corrections Issued 10/8/2024 ALEXANDER JOO
Applicant returned to address corrections 11/7/2024 ALEXANDER JOO
Applicant returned to address corrections 11/23/2024 ALEXANDER JOO
Applicant returned to address corrections 11/25/2024 ZAW HAN
Plan Check Approved 12/16/2024 ZAW HAN
Issued 12/16/2024 APPLICANT
CofO in Progress 3/31/2026 ALIZAH MAYAGOITIA
Permit Finaled 4/2/2026 DEROLD HAUFF
CofO Issued 4/2/2026 DEROLD HAUFF
Permit Finaled 4/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/12/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 11/12/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/13/2024 TREVOR QUAN
Sewer availability Cleared 11/13/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 11/15/2024 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Sparks,, David Michael; Lic. No.: C65739 2996 SLY FOX CIRCLE      ELIZABETH, CO 80107

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/29/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 2/10/2025 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/10/2025 Approved ALIZAH MAYAGOITIA
Sewer 2/10/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/4/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/28/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 3/28/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/25/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 4/25/2025 Approved ALIZAH MAYAGOITIA
Insulation 4/30/2025 Not Ready for Inspection ANTHONY RAMOS
BUILDING-Rough-Frame 5/1/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 5/1/2025 Corrections Issued LILIANA PORTILLO
Insulation 5/1/2025 Corrections Issued LILIANA PORTILLO
Drywall Nailing 5/8/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 5/8/2025 Approved ALIZAH MAYAGOITIA
Insulation 5/8/2025 Approved ALIZAH MAYAGOITIA
Wood Frame 5/8/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/7/2025 Approved ALIZAH MAYAGOITIA
Final 7/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 7/7/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/7/2025 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 7/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/7/2025 Approved ALIZAH MAYAGOITIA
Final 10/24/2025 Corrections Issued ALIZAH MAYAGOITIA
Service/Power Release 10/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 3/24/2026 Not Ready for Inspection RONNIE MEDINA
Service/Power Release 3/24/2026 Approved RONNIE MEDINA
Final 3/26/2026 Conditional Approval ALIZAH MAYAGOITIA
Final 3/31/2026 OK to Issue CofO ALIZAH MAYAGOITIA