5710 E VIA MARISOL 90042

Certificate Information: 5710 E VIA MARISOL 90042

Application / Permit
24010-10000-04166
Plan Check / Job No.
B24LA25385
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story detached ADU per LAMC 12.2 A.33 (c)-(d)
Permit Issued
Issued on 7/1/2025
Issuing Office
Metro
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 MATTHEW TORRES
Corrections Issued 10/15/2024 MATTHEW TORRES
Quality Review Completed 10/17/2024 RODOLFO ARIAS
Building Plans Picked Up 10/24/2024 APPLICANT
Applicant returned to address corrections 5/1/2025 MATTHEW TORRES
Applicant returned to address corrections 5/27/2025 MATTHEW TORRES
Plan Check Approved 7/1/2025 MATTHEW TORRES
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/8/2024 RUSSELL BONVOULOIR
Address approval Cleared 11/12/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/13/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/25/2025 JUSTIN BICOL
Sewer availability Cleared 3/5/2025 JUSTIN BICOL
GPI Written Notices Cleared 7/1/2025 MATTHEW TORRES

Contact Information

Contractor Owner-Builder       ,
Engineer Fernandez,, Agapito B; Lic. No.: C56546 7400 E SLAUSON AVE STE S      COMMERCE, CA 90040
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/8/2025 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 10/15/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Corrections Issued RONNIE MEDINA
ELECTRICAL-Rough 12/17/2025 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval LILIANA PORTILLO
HVAC-Rough 12/17/2025 Corrections Issued LILIANA PORTILLO
MERV13>=Rough 12/17/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 12/17/2025 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 12/17/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/30/2025 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Rough 12/30/2025 Approved DAVID WILLIAMS
Green Building Rough 12/30/2025 Approved DAVID WILLIAMS
HVAC-Rough 12/30/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 12/30/2025 Approved DAVID WILLIAMS
Structural Steel Frame 1/5/2026 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/14/2026 Approved LILIANA PORTILLO
Interior/Exterior Lathing 1/14/2026 Partial Approval LILIANA PORTILLO
Insulation 2/3/2026 Approved LILIANA PORTILLO
Drywall Nailing 2/18/2026 Approved LILIANA PORTILLO
Final 5/20/2026 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/20/2026 Approved LILIANA PORTILLO
Green Building Final 5/20/2026 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 5/20/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/20/2026 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 5/20/2026 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 5/20/2026 Approved LILIANA PORTILLO