5475 W 76TH ST 90045
Certificate Information: 5475 W 76TH ST 90045
- Application / Permit
- 24010-10000-04151
- Plan Check / Job No.
- B24LA25271
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 839 SF detached ADU at rear of lot.
- Permit Issued
- Issued on 6/30/2025
- Issuing Office
- Current Status
- Issued on 6/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2024 | DANIEL SANJUAN |
| Corrections Issued | 11/12/2024 | DANIEL SANJUAN |
| Applicant returned to address corrections | 5/16/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 6/7/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 6/23/2025 | DANIEL SANJUAN |
| Issued | 6/30/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2025 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 1/21/2025 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 4/7/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 4/24/2025 | XOCHITL ARQUIETA |
| Roof/Waste drainage to street | Cleared | 5/14/2025 | XOCHITL ARQUIETA |
| Construction near power lines | Cleared | 6/16/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/16/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Jimenez Builders Inc; Lic. No.: 1049508-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/15/2025 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 7/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/18/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 7/18/2025 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 7/29/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 8/22/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 8/22/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/28/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/28/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 8/28/2025 | Approved | JESUS PINEDA |
| Shower Pan | 8/28/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 9/3/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | RUBEN RIVAS |
| MERV13>=Rough | 9/3/2025 | Approved | RUBEN RIVAS |
| Verify Sprinkler Sign Off | 9/3/2025 | Approved | RUBEN RIVAS |
| Insulation | 9/4/2025 | Corrections Issued | RUBEN RIVAS |
| Insulation | 9/5/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 9/9/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/9/2025 | Approved | RUBEN RIVAS |
| Service/Power Release | 9/17/2025 | Partial Approval | JESUS PINEDA |
| Sewer | 9/17/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 9/17/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 11/5/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 11/5/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 11/5/2025 | Approved | JESUS PINEDA |
| Service/Power Release | 11/5/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 11/5/2025 | Approved | JESUS PINEDA |
| Final | 11/14/2025 | Partial Approval | JESUS PINEDA |
| Green Building Final | 11/14/2025 | Approved | JESUS PINEDA |
| MERV13>=Final | 11/14/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Required | JESUS PINEDA |