5475 W 76TH ST 90045

Certificate Information: 5475 W 76TH ST 90045

Application / Permit
24010-10000-04151
Plan Check / Job No.
B24LA25271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New 839 SF detached ADU at rear of lot.
Permit Issued
Issued on 6/30/2025
Issuing Office
Current Status
Issued on 6/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/5/2024 APPLICANT
Assigned to Plan Check Engineer 11/8/2024 DANIEL SANJUAN
Corrections Issued 11/12/2024 DANIEL SANJUAN
Applicant returned to address corrections 5/16/2025 DANIEL SANJUAN
Applicant returned to address corrections 6/7/2025 NEHEMIAS RAMOS
Plan Check Approved 6/23/2025 DANIEL SANJUAN
Issued 6/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/6/2025 ANTHONY MAINEZ
Specific Plan Cleared 1/21/2025 FREDDY GARCIA
Grading Pre-Inspection Cleared 4/7/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 4/24/2025 XOCHITL ARQUIETA
Sewer availability Cleared 4/24/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 5/14/2025 XOCHITL ARQUIETA
Construction near power lines Cleared 6/16/2025 RIDWAN HARDY
Construction within easement Cleared 6/16/2025 RIDWAN HARDY

Contact Information

Contractor Jimenez Builders Inc; Lic. No.: 1049508-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2025 Corrections Issued ANTHONY EGSON
Underground Mechanical 7/15/2025 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 7/18/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 7/18/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 7/29/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 8/22/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Approved JESUS PINEDA
PLUMBING-Rough 8/22/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 8/28/2025 Approved JESUS PINEDA
HVAC-Rough 8/28/2025 Approved JESUS PINEDA
PLUMBING-Rough 8/28/2025 Approved JESUS PINEDA
Shower Pan 8/28/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 9/3/2025 Approved RUBEN RIVAS
Green Building Rough 9/3/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 9/3/2025 Partial Approval RUBEN RIVAS
MERV13>=Rough 9/3/2025 Approved RUBEN RIVAS
Verify Sprinkler Sign Off 9/3/2025 Approved RUBEN RIVAS
Insulation 9/4/2025 Corrections Issued RUBEN RIVAS
Insulation 9/5/2025 Approved RUBEN RIVAS
Drywall Nailing 9/9/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 9/9/2025 Approved RUBEN RIVAS
Service/Power Release 9/17/2025 Partial Approval JESUS PINEDA
Sewer 9/17/2025 Approved JESUS PINEDA
Special/Order Compliance 9/17/2025 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 11/5/2025 Approved JESUS PINEDA
HVAC-Final 11/5/2025 Approved JESUS PINEDA
PLUMBING-Final 11/5/2025 Approved JESUS PINEDA
Service/Power Release 11/5/2025 Approved JESUS PINEDA
Smoke Detectors 11/5/2025 Approved JESUS PINEDA
Final 11/14/2025 Partial Approval JESUS PINEDA
Green Building Final 11/14/2025 Approved JESUS PINEDA
MERV13>=Final 11/14/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Not Required JESUS PINEDA