613 1/2 N CORONADO ST 90026
Certificate Information: 613 1/2 N CORONADO ST 90026
- Application / Permit
- 24010-10000-04124
- Plan Check / Job No.
- B24LA24940
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New detached 2 story structure with a 3 car carport on first floor. ADU on second floor per LAMC 12.22A.33 (c) and (e).
- Permit Issued
- Issued on 4/30/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 10/23/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 11/4/2024 | TU HUA |
| Applicant returned to address corrections | 4/8/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 4/23/2025 | MARCELA FRANQUEZ |
| Issued | 4/30/2025 | APPLICANT |
| CofO in Progress | 6/2/2026 | FREDDIE RIVERA |
| No Progress | 6/3/2026 | FREDDIE RIVERA |
| CofO in Progress | 6/3/2026 | FREDDIE RIVERA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/20/2024 | CHRISTINA BRACO |
| Address approval | Cleared | 2/20/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/8/2025 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 4/8/2025 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu Dan; Lic. No.: NA72038 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2025 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/11/2025 | Approved | WILLIAM SIERRA |
| METHANE-Barrier | 12/11/2025 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 12/11/2025 | Approved | WILLIAM SIERRA |
| Sewer | 12/11/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | FREDDIE RIVERA |
| Special/Order Compliance | 1/5/2026 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/26/2026 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/26/2026 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 1/26/2026 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 1/26/2026 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/26/2026 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/17/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2026 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/17/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/17/2026 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 3/4/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 3/4/2026 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 3/4/2026 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 3/4/2026 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/4/2026 | Approved | FREDDIE RIVERA |
| Insulation | 3/13/2026 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/18/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 3/18/2026 | Approved | GEM DE OCAMPO |
| Gas Test | 5/18/2026 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/18/2026 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/27/2026 | Approved | FREDDIE RIVERA |
| Final | 5/27/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/27/2026 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 5/27/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 5/27/2026 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 5/27/2026 | Approved | FREDDIE RIVERA |
| Final | 6/2/2026 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 6/2/2026 | Approved | FREDDIE RIVERA |