2131 S BENECIA AVE 90025
Certificate Information: 2131 S BENECIA AVE 90025
- Application / Permit
- 24010-10000-04100
- Plan Check / Job No.
- B24LA24778
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE NFPA 13R SOLAR INSTALLATION REQUIRED TO MEET 3.31 KW PER TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 3/5/2025
- Issuing Office
- Current Status
- Issued on 3/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | VIVIAN LAO |
| Corrections Issued | 10/10/2024 | VIVIAN LAO |
| Quality Review Completed | 10/11/2024 | GARO TELMI |
| Applicant returned to address corrections | 12/26/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 1/29/2025 | VIVIAN LAO |
| Plan Check Approved | 2/26/2025 | VIVIAN LAO |
| Issued | 3/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2024 | DARIN LAM |
| Sewer availability | Cleared | 11/18/2024 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 12/6/2024 | SARAH YOUSSEF |
| Trees in Parkway | Cleared | 1/3/2025 | MIGUEL ORNELAS |
| Permit | Cleared | 1/22/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/22/2025 | DARIN LAM |
| Hydrant and Access approval | Cleared | 1/28/2025 | KURT CORRAL |
| Specific Plan | Cleared | 1/28/2025 | HAMID GHAEMMAGHAMI |
| GPI Written Notices | Cleared | 2/5/2025 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 2/5/2025 | VIVIAN LAO |
Contact Information
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | , |
| Engineer | Mccullum,, Eric William; Lic. No.: C68850 | 727 2ND ST STE 104 HERMOSA BEACH, CA 90254 |
| Engineer | Tucker,, Keith D; Lic. No.: GE841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 4/18/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 4/18/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 4/18/2025 | Approved | DANIEL VERA |
| Sewer | 4/18/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 4/28/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 4/28/2025 | Not Ready for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 4/29/2025 | Approved | DANIEL VERA |
| METHANE-Barrier | 4/29/2025 | Approved | DANIEL VERA |
| Green Building Rough | 5/21/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 5/21/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 5/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Sewer | 5/21/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 5/21/2025 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 5/27/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 5/27/2025 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 5/27/2025 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 5/28/2025 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 5/29/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Approval | DANIEL VERA |
| METHANE-Rough | 8/4/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 8/4/2025 | Approved | DANIEL VERA |
| Special/Order Compliance | 8/4/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Shower Pan | 8/21/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 9/9/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 9/17/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 9/17/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 10/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 10/22/2025 | Approved | DANIEL VERA |
| Insulation | 11/3/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | DANIEL VERA |
| Green Building Rough | 11/5/2025 | Approved | DANIEL VERA |
| METHANE-Rough | 11/5/2025 | Approved | DANIEL VERA |
| Verify Sprinkler Sign Off | 11/5/2025 | Approved | DANIEL VERA |
| Insulation | 11/10/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 11/17/2025 | Approved | DANIEL VERA |