3526 S 7TH AVE 90018
Certificate Information: 3526 S 7TH AVE 90018
- Application / Permit
- 24010-10000-04090
- Plan Check / Job No.
- B24LA24683
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2 STORY ADU.
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | JOE VO |
| Corrections Issued | 10/8/2024 | JOE VO |
| Quality Review Completed | 10/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/17/2025 | JOE VO |
| Plan Check Approved | 4/16/2025 | JOE VO |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 12/29/2025 | WILLIAM SIERRA |
| Permit Finaled | 12/30/2025 | DEROLD HAUFF |
| CofO Issued | 12/30/2025 | DEROLD HAUFF |
| Permit Finaled | 12/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 11/12/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 1/28/2025 | FRANK GOMEZ |
| HPOZ | Cleared | 2/25/2025 | DANIEL MATA |
| Historic monument | Cleared | 2/25/2025 | DANIEL MATA |
| Roof/Waste drainage to street | Cleared | 4/16/2025 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/10/2025 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/31/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 7/31/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 7/31/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Deputy Wood Construction | 8/5/2025 | Conditional Approval | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 8/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 8/19/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 8/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/26/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 8/26/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Green Building Rough | 8/29/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 9/5/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 9/16/2025 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 10/1/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/1/2025 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/15/2025 | Approved | DEVON JACKSON |
| Pre-Inspection | 11/12/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | JUSTIN HAWLEY |
| Final | 12/23/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 12/23/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 12/23/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Service/Power Release | 12/23/2025 | Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 12/23/2025 | Approved | JUSTIN HAWLEY |
| Final | 12/24/2025 | OK to Issue CofO | WILLIAM SIERRA |