3526 S 7TH AVE 90018

Certificate Information: 3526 S 7TH AVE 90018

Application / Permit
24010-10000-04090
Plan Check / Job No.
B24LA24683
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2 STORY ADU.
Permit Issued
Issued on 4/17/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 JOE VO
Corrections Issued 10/8/2024 JOE VO
Quality Review Completed 10/9/2024 GARO TELMI
Applicant returned to address corrections 3/17/2025 JOE VO
Plan Check Approved 4/16/2025 JOE VO
Issued 4/17/2025 APPLICANT
CofO in Progress 12/29/2025 WILLIAM SIERRA
Permit Finaled 12/30/2025 DEROLD HAUFF
CofO Issued 12/30/2025 DEROLD HAUFF
Permit Finaled 12/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/29/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 11/12/2024 JESSICA OPINION
Sewer availability Cleared 11/12/2024 JESSICA OPINION
Hydrant and Access approval Cleared 1/28/2025 FRANK GOMEZ
HPOZ Cleared 2/25/2025 DANIEL MATA
Historic monument Cleared 2/25/2025 DANIEL MATA
Roof/Waste drainage to street Cleared 4/16/2025 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/19/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/23/2025 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 7/10/2025 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 7/31/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 7/31/2025 Not Ready for Inspection ARTHUR NEGRETE
Verify Sprinkler Sign Off 7/31/2025 Not Ready for Inspection ARTHUR NEGRETE
Deputy Wood Construction 8/5/2025 Conditional Approval ANTHONY RAMOS
BUILDING-Rough-Frame 8/19/2025 Corrections Issued JUSTIN HAWLEY
Green Building Rough 8/19/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 8/19/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 8/26/2025 Corrections Issued JUSTIN HAWLEY
Green Building Rough 8/26/2025 Not Ready for Inspection JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 8/26/2025 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 8/29/2025 Not Ready for Inspection WILLIAM SIERRA
Green Building Rough 8/29/2025 Not Ready for Inspection WILLIAM SIERRA
BUILDING-Rough-Frame 9/5/2025 Approved JUSTIN HAWLEY
Green Building Rough 9/5/2025 Not Ready for Inspection JUSTIN HAWLEY
Insulation 9/16/2025 Approved JUSTIN HAWLEY
Drywall Nailing 10/1/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/1/2025 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 10/15/2025 Approved DEVON JACKSON
Pre-Inspection 11/12/2025 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 12/23/2025 Approved JUSTIN HAWLEY
Final 12/23/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 12/23/2025 Approved JUSTIN HAWLEY
Green Building Rough 12/23/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Required JUSTIN HAWLEY
Service/Power Release 12/23/2025 Not Required JUSTIN HAWLEY
Smoke Detectors 12/23/2025 Approved JUSTIN HAWLEY
Final 12/24/2025 OK to Issue CofO WILLIAM SIERRA