3965 S LA SALLE AVE 90062

Certificate Information: 3965 S LA SALLE AVE 90062

Application / Permit
24010-10000-04083
Plan Check / Job No.
B24LA24556
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ADU per Ordinance R3 occupancy
Permit Issued
Issued on 8/5/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 LUKE GONZALES
Corrections Issued 10/5/2024 LUKE GONZALES
Building Plans Picked Up 11/5/2024 APPLICANT
Applicant returned to address corrections 3/24/2025 JOSE VELAZQUEZ
Plan Check Approved 5/15/2025 KELVIN CHUONG
Issued 8/5/2025 APPLICANT
CofO in Progress 7/7/2026 SABAS ALONSO
Permit Finaled 7/9/2026 DEROLD HAUFF
CofO Issued 7/9/2026 DEROLD HAUFF
Permit Finaled 7/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/10/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/10/2024 JUSTIN BICOL
Construction near power lines Cleared 1/8/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/6/2025 JUSTIN BICOL
Sewer availability Cleared 3/6/2025 JUSTIN BICOL

Contact Information

Contractor Ameera Enterprises Inc; Lic. No.: 935432-B 22187 BAUHINIA CT      WOODLAND HILLS, CA 91367
Engineer Yoon,, Philip; Lic. No.: C94664 1221 W 3RD ST   APT 234    LOS ANGELES, CA 90017

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/7/2025 Partial Approval SABAS ALONSO
Sewer 8/7/2025 Approved SABAS ALONSO
Underground Mechanical 8/7/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 8/19/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 10/1/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 10/1/2025 Approved SABAS ALONSO
PLUMBING-Rough 10/1/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/8/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 10/8/2025 Approved SABAS ALONSO
Green Building Rough 10/8/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/8/2025 Partial Approval SABAS ALONSO
Insulation 10/10/2025 Approved DEVON JACKSON
Drywall Nailing 10/15/2025 Approved ANTHONY RAMOS
Shower Pan 10/28/2025 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 10/29/2025 Approved SABAS ALONSO
Shower Pan 10/29/2025 Corrections Issued SABAS ALONSO
Shower Pan 10/31/2025 Approved ANTHONY RAMOS
Underground Mechanical 1/27/2026 Approved SABAS ALONSO
ELECTRICAL-Final 4/28/2026 Approved SABAS ALONSO
Final 4/28/2026 Corrections Issued SABAS ALONSO
Green Building Final 4/28/2026 Approved SABAS ALONSO
HVAC-Final 4/28/2026 Approved SABAS ALONSO
PLUMBING-Final 4/28/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved SABAS ALONSO
Service/Power Release 4/28/2026 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 4/28/2026 Approved SABAS ALONSO
Final 5/1/2026 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 6/23/2026 Approved SABAS ALONSO
Final 6/23/2026 Corrections Issued SABAS ALONSO
HVAC-Final 6/23/2026 Approved SABAS ALONSO
Service/Power Release 6/23/2026 Not Ready for Inspection SABAS ALONSO
Final 7/1/2026 OK to Issue CofO SABAS ALONSO
Service/Power Release 7/1/2026 Approved SABAS ALONSO