1456 W 49TH ST 90062

Certificate Information: 1456 W 49TH ST 90062

Application / Permit
24010-10000-04052
Plan Check / Job No.
B24LA24283
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. NEW 1 STORY DETACHED ADU (790 SF) PER ENGR DESIGN.
Permit Issued
Issued on 1/2/2025
Issuing Office
Current Status
CofO Issued on 4/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 NGHI SU
Corrections Issued 10/4/2024 NGHI SU
Applicant returned to address corrections 11/23/2024 NGHI SU
Applicant returned to address corrections 12/4/2024 NEHEMIAS RAMOS
Plan Check Approved 12/23/2024 NEHEMIAS RAMOS
Issued 1/2/2025 APPLICANT
CofO in Progress 4/22/2026 RAUL BARAJAS
Permit Finaled 4/26/2026 DEROLD HAUFF
CofO Issued 4/26/2026 DEROLD HAUFF
Permit Finaled 4/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/7/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/7/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/10/2024 JUSTIN BICOL
Sewer availability Cleared 10/10/2024 JUSTIN BICOL
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2025 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/20/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 2/20/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
Underground Mechanical 2/20/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/24/2025 Approved BARRY HACHE
Underground Mechanical 2/24/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 3/6/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Corrections Issued BARRY HACHE
Green Building Rough 6/3/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 6/3/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 6/5/2025 Approved BARRY HACHE
ELECTRICAL-Rough 7/28/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 8/6/2025 Corrections Issued BARRY HACHE
HVAC-Rough 8/6/2025 Corrections Issued BARRY HACHE
Interior/Exterior Lathing 8/6/2025 Partial Approval BARRY HACHE
ELECTRICAL-Rough 8/14/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 8/14/2025 Not Ready for Inspection BARRY HACHE
HVAC-Rough 8/18/2025 Approved BARRY HACHE
PLUMBING-Rough 8/18/2025 Approved BARRY HACHE
Green Building Rough 8/20/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 8/20/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 8/20/2025 Approved BARRY HACHE
Interior/Exterior Lathing 8/28/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 9/22/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Approved BARRY HACHE
Green Building Rough 9/22/2025 Approved BARRY HACHE
Insulation 10/7/2025 Approved BARRY HACHE
Drywall Nailing 10/22/2025 Approved BARRY HACHE
Interior/Exterior Lathing 10/27/2025 Approved BARRY HACHE
Shower Pan 10/27/2025 Approved BARRY HACHE
Final 2/2/2026 Corrections Issued BARRY HACHE
HVAC-Final 2/2/2026 Corrections Issued BARRY HACHE
PLUMBING-Final 2/2/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Final 3/10/2026 Corrections Issued BARRY HACHE
Final 3/10/2026 Corrections Issued BARRY HACHE
Gas Test 3/10/2026 Approved BARRY HACHE
Green Building Final 3/10/2026 Not Ready for Inspection BARRY HACHE
HVAC-Final 3/10/2026 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 3/10/2026 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Required BARRY HACHE
Smoke Detectors 3/10/2026 Approved BARRY HACHE
ELECTRICAL-Final 4/1/2026 Corrections Issued BARRY HACHE
Final 4/1/2026 Corrections Issued BARRY HACHE
Green Building Final 4/1/2026 Not Ready for Inspection BARRY HACHE
HVAC-Final 4/1/2026 Corrections Issued BARRY HACHE
PLUMBING-Final 4/1/2026 Corrections Issued BARRY HACHE
Service/Power Release 4/1/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 4/9/2026 Corrections Issued RAUL BARAJAS
Final 4/9/2026 Corrections Issued RAUL BARAJAS
Green Building Final 4/9/2026 Approved RAUL BARAJAS
HVAC-Final 4/9/2026 Approved RAUL BARAJAS
PLUMBING-Final 4/9/2026 Approved RAUL BARAJAS
Service/Power Release 4/9/2026 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 4/22/2026 Approved RAUL BARAJAS
Final 4/22/2026 OK to Issue CofO RAUL BARAJAS
Gas Test 4/22/2026 Approved RAUL BARAJAS
HVAC-Final 4/22/2026 Approved RAUL BARAJAS
PLUMBING-Final 4/22/2026 Approved RAUL BARAJAS
Service/Power Release 4/22/2026 Approved RAUL BARAJAS