903-903 1/2 W 80TH ST 90044
Certificate Information: 903-903 1/2 W 80TH ST 90044
- Application / Permit
- 24010-10000-04044
- Plan Check / Job No.
- B24LA24247
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN New PROPOSED TWO-STORY ADU ONE ON TOP OF THE OTHER: ADU#1 AT 1ST FLOOR - 3 BEDROOM, 2 BATH, 900 SF ADU#2 AT 2ND FLOOR - 3 BEDROOM, 2 BATH, 900 SF ***13D SPRINKLER REQUIRED***
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- Issued on 5/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | KHUONG TRUONG |
| Corrections Issued | 9/30/2024 | KHUONG TRUONG |
| Quality Review Completed | 10/1/2024 | GARO TELMI |
| Applicant returned to address corrections | 12/23/2024 | KHUONG TRUONG |
| Plan Check Approved | 4/2/2025 | KHUONG TRUONG |
| Issued | 5/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/22/2024 | EDGAR PASCUA |
| Address approval | Cleared | 10/30/2024 | AMBER CAMPBELL |
| Low Impact Development (LID) | Cleared | 11/1/2024 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 11/12/2024 | AMBER CAMPBELL |
| "Q" conditions | Cleared | 12/9/2024 | MANERI ROMAN |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/24/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Socal Supreme Home Builders Llc; Lic. No.: 1133905-B | , |
| Engineer | Sayah,, Daniel H; Lic. No.: NA67905 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/18/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 7/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 8/8/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 8/14/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 8/14/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 8/19/2025 | Conditional Approval | LUIS CASTRO |
| PLUMBING-Rough | 8/19/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 12/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 12/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/24/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/16/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 1/16/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 2/6/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 2/6/2026 | Approved | JOHN QUINTANILLA |