12406 W CANTARA ST 91605

Certificate Information: 12406 W CANTARA ST 91605

Application / Permit
24010-10000-04001
Plan Check / Job No.
B24LA23903
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ADU AT REAR OF LOT PER LAMC 12.22A.33(c)-(d)
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 SAM CHANG
Corrections Issued 10/7/2024 SAM CHANG
Quality Review Completed 10/9/2024 EUGENE BARBEAU
Building Plans Picked Up 10/31/2024 APPLICANT
Plan Check Approved 1/17/2025 SAM CHANG
Issued 1/24/2025 APPLICANT
CofO in Progress 6/12/2025 MATTHEW NELSON
Permit Finaled 6/26/2025 RUBEN SALAS
CofO Issued 6/26/2025 RUBEN SALAS
Permit Finaled 6/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/27/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/27/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/27/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/27/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 12/19/2024 GEVORK KARAPETYAN

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2025 Partial Inspection MATTHEW NELSON
Underground Mechanical 2/18/2025 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 2/22/2025 Corrections Issued DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/22/2025 Off-Hour Fees Due
Footing/Foundation/Slab 2/22/2025 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 2/22/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/25/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Inspection LOUIS ESCOTO
Pre-Inspection 3/7/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 4/4/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 4/4/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 4/4/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/10/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 4/10/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 4/10/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/28/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 4/28/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 4/28/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
Wood Frame 5/1/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/5/2025 Approved NICHOLAS TROWBRIDGE
Insulation 5/5/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/5/2025 Partial Approval NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 5/5/2025 Approved NICHOLAS TROWBRIDGE
Wood Frame 5/5/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
Drywall Nailing 5/9/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/12/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/20/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 6/5/2025 Not Ready for Inspection MATTHEW NELSON
Final 6/5/2025 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 6/5/2025 Approved MATTHEW NELSON
HVAC-Final 6/5/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 6/5/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 6/5/2025 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 6/5/2025 Approved MATTHEW NELSON
Underground Mechanical 6/5/2025 Approved MATTHEW NELSON
Final 6/9/2025 Corrections Issued MATTHEW NELSON
HVAC-Final 6/9/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Final 6/9/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Required MATTHEW NELSON
Service/Power Release 6/9/2025 Corrections Issued MATTHEW NELSON
Final 6/11/2025 OK to Issue CofO MATTHEW NELSON
Service/Power Release 6/11/2025 Approved MATTHEW NELSON