12406 W CANTARA ST 91605
Certificate Information: 12406 W CANTARA ST 91605
- Application / Permit
- 24010-10000-04001
- Plan Check / Job No.
- B24LA23903
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU AT REAR OF LOT PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Current Status
- CofO Issued on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | SAM CHANG |
| Corrections Issued | 10/7/2024 | SAM CHANG |
| Quality Review Completed | 10/9/2024 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/31/2024 | APPLICANT |
| Plan Check Approved | 1/17/2025 | SAM CHANG |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 6/12/2025 | MATTHEW NELSON |
| Permit Finaled | 6/26/2025 | RUBEN SALAS |
| CofO Issued | 6/26/2025 | RUBEN SALAS |
| Permit Finaled | 6/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/27/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/27/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 12/19/2024 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Partial Inspection | MATTHEW NELSON |
| Underground Mechanical | 2/18/2025 | Partial Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/22/2025 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 2/22/2025 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/22/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/22/2025 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Inspection | LOUIS ESCOTO |
| Pre-Inspection | 3/7/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/4/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 4/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/4/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/10/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 4/10/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/10/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/1/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/1/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 5/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 5/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Wood Frame | 5/5/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 5/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 5/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 5/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 5/20/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 6/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 6/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/5/2025 | Approved | MATTHEW NELSON |
| HVAC-Final | 6/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 6/5/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 6/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 6/5/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 6/5/2025 | Approved | MATTHEW NELSON |
| Final | 6/9/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 6/9/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 6/9/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Not Required | MATTHEW NELSON |
| Service/Power Release | 6/9/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 6/11/2025 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 6/11/2025 | Approved | MATTHEW NELSON |